MOUNT BLAIRY SOLAR FARM BROWNSIDE FARM

MOUNT BLAIRY SOLAR FARM at MACDUFF

SSEN Embedded Capacity Register, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
6 Oct 2027
Status
Accepted to connect
Customer
MOUNT BLAIRY SOLAR FARM
Site name
MOUNT BLAIRY SOLAR FARM BROWNSIDE FARM
Address
BROWNSIDE FARM, BANFF, ABERDEENSHIRE, AB45 3YD
Grid reference
Easting 367023, northing 854381
Licence area
North of Scotland (SHEPD)
Grid supply point
MACDUFF
Bulk supply point
Not stated
Primary substation
MACDUFF GRID
Connection voltage
33 kV
Technology group
Solar
Energy source 1
SOLAR, PHOTOVOLTAIC: 35.2 MW registered
Registered capacity
35.2 MW
Change to maximum export capacity
0.8 MW
Change to maximum import capacity
0.8 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
6 Oct 2026
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
12 Jun 2026
Tracked since
June 2026 edition

Change history

Tracked since the June 2026 edition, across 6 editions.

Changes to the details QueueWatch tracks, newest first.

  • November 2026 edition
    Export capacity changed from 35.2 MW to 0.8 MW
  • October 2026 edition
    Export capacity changed from 0.8 MW to 35.2 MW
  • August 2026 edition
    Export capacity changed from 35.2 MW to 0.8 MW

Also at MACDUFF

GSP view

20 other sites at this grid supply point in the November 2026 edition, 16 of them at MACDUFF GRID, the same primary substation. In all, the sites here total 398 MW: 79 MW connected, 319 MW accepted to connect.

See all 20

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?