WERRAR FARM
At FAWLEY GSP
SSEN Embedded Capacity Register, November 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 2 Apr 2026
- Status
- Accepted to connect
- Customer
- Not stated
- Site name
- WERRAR FARM
- Address
- WERRAR FARM, WERRAR LANE, NEWPORT, ISLE OF WIGHT, PO30 5TU
- Grid reference
- Easting 450276, northing 92693
- Licence area
- Southern England (SEPD)
- Grid supply point
- FAWLEY GSP
- Bulk supply point
- COWES & WOOTTON COMMON
- Primary substation
- Not stated
- Connection voltage
- 132 kV
- Technology group
- Solar
- Energy source 1
- SOLAR, PHOTOVOLTAIC: 45 MW registered
- Energy source 2
- STORED ENERGY (ALL STORED ENERGY IRRESPECTVE OF THE ORIGINAL ENERGY SOURCE), STORAGE - ELECTROCHEMICAL (BATTERIES): 9.474 MW registered
- Registered capacity
- 45 MW
- Change to maximum export capacity
- 9.474 MW
- Change to maximum import capacity
- 9.474 MW
- Flexible connection
- Not stated
- In a connection queue
- Not published by SSEN
- Date accepted
- 2 Apr 2025
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by SSEN
- Transmission reinforcement reference
- Not published by SSEN
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 10 Feb 2026
- Tracked since
- April 2025 edition
Change history
Tracked since the April 2025 edition, across 20 editions.
Changes to the details QueueWatch tracks, newest first.
- August 2026 editionExport capacity changed from 45 MW to 9.474 MW
- July 2026 editionExport capacity changed from 9.474 MW to 45 MW
- May 2026 editionExport capacity changed from 45 MW to 9.474 MW
- April 2026 editionExport capacity changed from 9.474 MW to 45 MW
- February 2026 editionExport capacity changed from 35 MW to 9.474 MW
- November 2025 editionTarget energisation date stated as 2 Apr 2026 (not stated in the October 2025 edition)
Also at FAWLEY GSP
GSP view26 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 692 MW: 473 MW connected, 219 MW accepted to connect.
- ARRETON VALLEY NURSERYTHE ISLE OF WIGHT ENERGY COMPANY LIMITED, Solar, ARRETON NURSERIES primaryConnected33.25 MW
- SOUTHERN WATER SERVICES LIMITEDEUROPEAN MARINE ENERGY CENTRE (EMEC), Hydro and marine, VENTNOR primaryAccepted19.836 MW
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose