Horton Wood Solar Farm

NextPower Horton Wood Limited at Northfleet East

UKPN Embedded Capacity Register 2 – 1MW and above, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
20 Jun 2026
Status
Accepted to connect
Planning consent
Granted 17 Feb 2023
Sevenoaks, reference 22/02599/FUL · Source: REPD
Contract for Difference
Allocation Round 6
Customer
NextPower Horton Wood Limited
Site name
Horton Wood Solar Farm
Address
Off School Lane, Longfield, Kent, DA3 8AH
Grid reference
Easting 557680, northing 167191
Licence area
South Eastern Power Networks (SPN)
Grid supply point
Northfleet East
Bulk supply point
Not stated
Primary substation
Not stated
Connection voltage
132 kV
Technology group
Solar
Energy source 1
Solar, Photovoltaic: 49.9 MW registered
Registered capacity
49.9 MW
Change to maximum export capacity
49.9 MW
Change to maximum import capacity
Not stated
Flexible connection
No
In a connection queue
Yes
Date accepted
29 Sep 2020
Date connected
Not stated
Distribution reinforcement reference
Not published by UKPN
Transmission reinforcement reference
Not stated
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
13 Nov 2026
Tracked since
September 2026 edition

Change history

Tracked since the September 2026 edition, across 3 editions.

Changes to the details QueueWatch tracks, newest first.

  • November 2026 edition
    Target energisation date moved from 31 Oct 2025 to 20 Jun 2026 (8 months later)

Also at Northfleet East

GSP view

35 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 587 MW: 188 MW connected, 399 MW accepted to connect.

See all 35

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.

Contract for Difference

The Contracts for Difference allocation round for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition. QueueWatch matched the site to that record.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.