Andershaw Windfarm

Andershaw Wind Power Ltd at Linnmill

SPEN Embedded Capacity Register >1MW, September 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
31 Oct 2028
Status
Accepted to connect
Customer
Andershaw Wind Power Ltd
Site name
Andershaw Windfarm
Address
Andershaw Wind Farm, Crawfordjohn, Lanark, South Lanarkshire, ML12 6ZS
Grid reference
Easting 284709, northing 626009
Licence area
Central and Southern Scotland (SPD)
Grid supply point
Linnmill
Bulk supply point
Not stated
Primary substation
Not stated
Connection voltage
33 kV
Technology group
Wind
Energy source 1
Wind, Onshore wind turbines: 36 MW registered
Registered capacity
36 MW
Change to maximum export capacity
36 MW
Change to maximum import capacity
0 MW
Flexible connection
No
In a connection queue
Yes
Date accepted
Not stated
Date connected
Not stated
Distribution reinforcement reference
Not published by SPEN
Transmission reinforcement reference
Not stated
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
4 Apr 2023
Tracked since
March 2026 edition

Change history

Tracked since the March 2026 edition, across 7 editions.

Changes to the details QueueWatch tracks, newest first.

  • August 2026 edition
    Status changed from “connected” to “accepted to connect”
  • August 2026 edition
    Target energisation date stated as 31 Oct 2028 (not stated in the July 2026 edition)
  • August 2026 edition
    Flexible connection changed from “yes” to “no”
  • August 2026 edition
    In a connection queue changed from “no” to “yes”
  • July 2026 edition
    Status changed from “accepted to connect” to “connected”
  • July 2026 edition
    Target energisation date not stated (31 Oct 2028 in the June 2026 edition)
  • July 2026 edition
    Flexible connection changed from “no” to “yes”
  • July 2026 edition
    In a connection queue changed from “yes” to “no”
  • May 2026 edition
    Status changed from “connected” to “accepted to connect”
  • May 2026 edition
    Target energisation date stated as 31 Oct 2028 (not stated in the April 2026 edition)
  • May 2026 edition
    Flexible connection changed from “yes” to “no”

Also at Linnmill

GSP view

13 other sites at this grid supply point in the September 2026 edition. In all, the sites here total 216 MW: 120 MW connected, 96 MW accepted to connect.

See all 13

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?