(ANM) Low Fen Drove Way

Fen Ditton Solar And Battery Storage Limited at Burwell

UKPN Embedded Capacity Register 2 – 1MW and above, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
31 Oct 2031
Status
Accepted to connect
Planning consent
Application submitted 14 Mar 2025
South Cambridgeshire, reference 25/01014/FUL · Source: REPD
Customer
Fen Ditton Solar And Battery Storage Limited
Site name
(ANM) Low Fen Drove Way
Address
Fen Ditton, Horningsea, Cambridgeshire, CB25 9AT
Grid reference
Easting 550456, northing 260927
Licence area
Eastern Power Networks (EPN)
Grid supply point
Burwell
Bulk supply point
Not stated
Primary substation
Not stated
Connection voltage
132 kV
Technology group
Solar
Energy source 1
Solar, Photovoltaic: 49.9 MW registered
Registered capacity
49.9 MW
Change to maximum export capacity
49.9 MW
Change to maximum import capacity
10 MW
Flexible connection
Yes
In a connection queue
Yes
Date accepted
26 Aug 2021
Date connected
Not stated
Distribution reinforcement reference
Not published by UKPN
Transmission reinforcement reference
Not stated
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
14 Dec 2022
Tracked since
September 2026 edition

Change history

Tracked since the September 2026 edition, across 3 editions.

Changes to the details QueueWatch tracks, newest first.

No change to any detail QueueWatch tracks.

Also at Burwell

GSP view

38 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 1.1 GW: 0.4 GW connected, 0.7 GW accepted to connect.

See all 38

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.