QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

Purton End

Long Meadow Solar Farm Limited at Pelham

UKPN Embedded Capacity Register 2 – 1MW and above, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Date connected
11 Apr 2025
Status
Connected
Customer
Long Meadow Solar Farm Limited
Site name
Purton End
Address
Saffron Walden, Essex, CB11 3JT
Grid reference
Easting 555104, northing 234826
Licence area
Eastern Power Networks (EPN)
Grid supply point
Pelham
Bulk supply point
Thaxted Grid 33kV
Primary substation
Not stated
Connection voltage
33 kV
Technology group
Solar
Energy source 1
Solar, Photovoltaic: 12 MW registered
Registered capacity
12 MW
Maximum export capacity
12 MW
Maximum import capacity
0 MW
Flexible connection
No
In a connection queue
No
Date accepted
Not stated
Target energisation date
Not stated
Distribution reinforcement reference
Not published by UKPN
Transmission reinforcement reference
Not stated
Export MPAN
1050003331185
Import MPAN
Not stated
Last updated
14 Aug 2025
Tracked since
September 2026 edition

Change history

Tracked since the September 2026 edition, across 3 editions.

Changes to the details QueueWatch tracks, newest first.

No change to any detail QueueWatch tracks.

Also at Pelham

GSP view

41 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 839 MW: 234 MW connected, 605 MW accepted to connect.

See all 41

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?