Shenton Group

Customer named in the DNOs' registers

In UKPN's October 2026, SPEN's September 2026 and ENWL's September 2026 editions

The registers spell this customer’s name more than one way: “Shenton Group” (4 sites) and “SHENTON GROUP LTD” (1 site).

5sites of 1 MW and over
10.2 MWcapacity
9 MWconnected (4 sites)
1.2 MWaccepted to connect (1 sites)

Capacity by DNO

DNOEditionSitesCapacityConnectedAccepted to connect
UKPNOctober 2026 edition34.9 MW4.9 MW–
SPENSeptember 2026 edition14.1 MW4.1 MW–
ENWLSeptember 2026 edition11.2 MW–1.2 MW

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Gas and other fossil48.4 MW7.2 MW1.2 MW
Bioenergy and waste11.8 MW1.8 MW–

Each site is grouped by its first energy source, as the register names it.

Sites

Each site under this name in the DNOs' latest editions, the largest first.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

SiteDNOGrid supply pointTechnologyStatusMW
Innospec 1SPENCapenhurstGas and other fossilConnected4.14
Pladis Harlesden ChpUKPNWillesden 132kVGas and other fossilConnected1.86
Green TyeUKPNPelhamBioenergy and wasteConnected1.8
Bromley HospitalUKPNNorthfleet EastGas and other fossilConnected1.2
MANCHESTER AIRPORT, TERMINAL 2ENWLSOUTH MANCHESTER GSPGas and other fossilAccepted to connect1.2

Grid supply points

Each grid supply point its sites are at, with the capacity of its own sites there.

Grid supply pointDNOSitesConnectedAccepted to connect
CapenhurstSPEN14.1 MW–
Willesden 132kVUKPN11.9 MW–
PelhamUKPN11.8 MW–
Northfleet EastUKPN11.2 MW–
SOUTH MANCHESTER GSPENWL1–1.2 MW

What changed recently

Changes to its sites found in both of two consecutive monthly editions of their DNO's register, the latest first.

UKPN, September 2026 edition to October 2026 edition, for this customer's sites: 3 sites matched. Every September site and every October site had a match in the other edition.

SPEN, August 2026 edition to September 2026 edition, for this customer's sites: 1 site matched. Every August site and every September site had a match in the other edition.

ENWL, May 2026 edition to September 2026 edition, for this customer's sites: 1 site matched. Every May site and every September site had a match in the other edition.

No change to the status, capacity, technology or customer of its sites in the editions QueueWatch holds.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose