West Weybridge
Grid supply point in South Eastern Power Networks (SPN)
UKPN Embedded Capacity Register 2 – 1MW and above, November 2026 edition
Capacity by technology
| Technology | Sites | Capacity | Connected | Accepted to connect |
|---|---|---|---|---|
| Solar | 3 | 54.8 MW | 4.9 MW | 49.9 MW |
| Gas and other fossil | 5 | 26.2 MW | 4.2 MW | 22 MW |
| Storage | 1 | 6 MW | 6 MW | – |
| Bioenergy and waste | 1 | 1.5 MW | 1.5 MW | – |
Storage capacity in MWh: no site here states any.
Each site is grouped by its first energy source, as the register names it.
How busy is each primary substation?
Each primary substation at this grid supply point in the November 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.
Site, company and substation names are shown as they appear in the registers, including capitalisation.
| Primary substation | Bulk supply point | Sites | Connected | Accepted to connect | |||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Leatherhead 132kV | 1 | – | 49.9 MW | ||||||||||||||||
1 site, 49.9 MW: 49.9 MW accepted to connect
| |||||||||||||||||||
| W. Weybridge 132/33 | 1 | – | 18 MW | ||||||||||||||||
1 site, 18 MW: 18 MW accepted to connect
| |||||||||||||||||||
| Leatherhead Grid 33kV | 1 | 6 MW | – | ||||||||||||||||
1 site, 6 MW: 6 MW connected
| |||||||||||||||||||
| Leatherhead Grid 33kV | 1 | 3.4 MW | – | ||||||||||||||||
1 site, 3.4 MW: 3.4 MW connected
| |||||||||||||||||||
| Guildford Grid 132kV | 1 | – | 4 MW | ||||||||||||||||
1 site, 4 MW: 4 MW accepted to connect
| |||||||||||||||||||
| Guildford Grid 33kV | 2 | 3 MW | – | ||||||||||||||||
2 sites, 3 MW: 3 MW connected
| |||||||||||||||||||
| West Weybridge Grid 33kV | 1 | 1.5 MW | – | ||||||||||||||||
1 site, 1.5 MW: 1.5 MW connected
| |||||||||||||||||||
| West Weybridge Grid 33kV | 1 | 1.2 MW | – | ||||||||||||||||
1 site, 1.2 MW: 1.2 MW connected
| |||||||||||||||||||
| Byfleet Grid 33kV | 1 | 1.5 MW | – | ||||||||||||||||
1 site, 1.5 MW: 1.5 MW connected
| |||||||||||||||||||
What changed recently
Changes to sites here found in both editions of each pair, newest first.
October 2026 edition to November 2026 edition: 10 sites matched. Every October site and every November site at this grid supply point had a match in the other edition.
- Guildford STWNovember 2026 editionTarget energisation date moved from 30 Apr 2025 to 10 Jul 2025 (2 months later)
- Slyfield FarmNovember 2026 editionTarget energisation date moved from 1 Jan 2025 to 31 Jan 2029 (49 months later)
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?
How power reaches a site
A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.