Hackney 66kV
Grid supply point in London Power Networks (LPN)
UKPN Embedded Capacity Register 2 – 1MW and above, October 2026 edition
Capacity by technology
| Technology | Sites | Capacity | Connected | Accepted to connect |
|---|---|---|---|---|
| Gas and other fossil | 2 | 8.8 MW | 8.8 MW | – |
Storage capacity in MWh: no site here states any.
Each site is grouped by its first energy source, as the register names it.
How busy is each primary substation?
Each primary substation at this grid supply point in the October 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.
Site, company and substation names are shown as they appear in the registers, including capitalisation.
| Primary substation | Bulk supply point | Sites | Connected | Accepted to connect | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Not stated | 1 | 7.2 MW | – | |||||||||||
1 site, 7.2 MW: 7.2 MW connected
| ||||||||||||||
| Not stated | 1 | 1.6 MW | – | |||||||||||
1 site, 1.6 MW: 1.6 MW connected
| ||||||||||||||
What changed recently
Changes to the sites here found in both of two consecutive monthly editions, the latest first.
September 2026 edition to October 2026 edition: 2 sites matched. Every September site and every October site at this grid supply point had a match in the other edition.
No change to the status, capacity, technology or customer of the sites here in the editions of UKPN's register QueueWatch holds.
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
How power reaches a site
A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.