Distribution / UKPN / Grid supply point

Rayleigh

Grid supply point in Eastern Power Networks (EPN)

UKPN Embedded Capacity Register 2 – 1MW and above, November 2026 edition

46sites of 1 MW and over
1.1 GWcapacity
0.5 GWconnected (31 sites)
0.6 GWaccepted to connect (15 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Solar27625 MW249 MW376 MW
Storage5255 MW155 MW100 MW
Wind4184 MW64 MW120 MW
Gas and other fossil753.5 MW45 MW8.5 MW
Bioenergy and waste312.2 MW12.2 MW–

Storage capacity in MWh: no site here states any.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the November 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
Maldon Grid 33kV114 MW–
Maldon Grid 33kV559.1 MW40 MW
Chelmsford East Grid 33kV1–8.6 MW
Chelmsford East Grid 33kV13.5 MW–
Chelmsford East Grid 33kV11.7 MW–
Chelmsford East Grid 33kV215 MW41.8 MW
Fleethall Grid 33kV15 MW–
Fleethall Grid 33kV13.2 MW–
Fleethall Grid 33kV12.6 MW–
Fleethall Grid 33kV339.1 MW17 MW
Nevendon Grid 33kV14.6 MW–
Nevendon Grid 33kV11.2 MW–
Nevendon Grid 33kV653 MW7 MW
Abberton Grid 33kV39.1 MW–
Abberton Grid 33kV444.8 MW–
Rayleigh Local 33kV2–30 MW
Southend Grid 33kV110 MW–
Not stated11260 MW459 MW

Search and filter all 46 sites at Rayleigh

Not found among the sites of 1 MW and over in UKPN’s November 2026 edition

2 sites last found at this grid supply point were not found among this edition’s sites of 1 MW and over by their MPAN, grid reference or name and postcode. QueueWatch keeps their pages for six months and does not say whether they have left the register.

What changed recently

Changes to sites here found in both editions of each pair, newest first.

October 2026 edition to November 2026 edition: 46 sites matched. 1 site at this grid supply point couldn’t be matched between the two editions, because its details changed or it appears in only one.

1 site without a match in the other edition
In the October 2026 edition only (1)
  • (ANM) ChelmsfordNovember 2026 editionTarget energisation date moved from 31 Dec 2028 to 11 Jan 2032 (36 months later)
  • (ANM) Crows LaneNovember 2026 editionTarget energisation date moved from 31 Dec 2028 to 11 Jan 2032 (36 months later)
  • (ANM) Marshes Burnham-On-CrouchNovember 2026 editionTarget energisation date moved from 31 Dec 2028 to 11 Jan 2032 (36 months later)
  • (ANM) South Woodham FerrersNovember 2026 editionTarget energisation date moved from 31 Dec 2028 to 11 Jan 2032 (36 months later)
  • Cards RoadNovember 2026 editionTarget energisation date moved from 6 Jan 2025 to 30 Mar 2026 (15 months later)
  • Fambridge FarmNovember 2026 editionTarget energisation date moved from 6 Jan 2025 to 30 Mar 2026 (15 months later)
  • Great Wheatley Solar FarmNovember 2026 editionTarget energisation date moved from 6 Jan 2025 to 30 Mar 2026 (15 months later)
  • Rayleigh SiteNovember 2026 editionTarget energisation date moved from 6 Jan 2025 to 30 Mar 2026 (15 months later)
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.