Rayleigh
Grid supply point in Eastern Power Networks (EPN)
UKPN Embedded Capacity Register 2 – 1MW and above, November 2026 edition
Capacity by technology
| Technology | Sites | Capacity | Connected | Accepted to connect |
|---|---|---|---|---|
| Solar | 27 | 625 MW | 249 MW | 376 MW |
| Storage | 5 | 255 MW | 155 MW | 100 MW |
| Wind | 4 | 184 MW | 64 MW | 120 MW |
| Gas and other fossil | 7 | 53.5 MW | 45 MW | 8.5 MW |
| Bioenergy and waste | 3 | 12.2 MW | 12.2 MW | – |
Storage capacity in MWh: no site here states any.
Each site is grouped by its first energy source, as the register names it.
How busy is each primary substation?
Each primary substation at this grid supply point in the November 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.
Site, company and substation names are shown as they appear in the registers, including capitalisation.
| Primary substation | Bulk supply point | Sites | Connected | Accepted to connect | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Maldon Grid 33kV | 1 | 14 MW | – | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 14 MW: 14 MW connected
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Maldon Grid 33kV | 5 | 59.1 MW | 40 MW | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
5 sites, 99.1 MW: 59.1 MW connected, 40 MW accepted to connect
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Chelmsford East Grid 33kV | 1 | – | 8.6 MW | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 8.6 MW: 8.6 MW accepted to connect
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Chelmsford East Grid 33kV | 1 | 3.5 MW | – | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 3.5 MW: 3.5 MW connected
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Chelmsford East Grid 33kV | 1 | 1.7 MW | – | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 1.7 MW: 1.7 MW connected
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Chelmsford East Grid 33kV | 2 | 15 MW | 41.8 MW | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2 sites, 56.8 MW: 15 MW connected, 41.8 MW accepted to connect
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Fleethall Grid 33kV | 1 | 5 MW | – | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 5 MW: 5 MW connected
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Fleethall Grid 33kV | 1 | 3.2 MW | – | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 3.2 MW: 3.2 MW connected
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Fleethall Grid 33kV | 1 | 2.6 MW | – | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 2.6 MW: 2.6 MW connected
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Fleethall Grid 33kV | 3 | 39.1 MW | 17 MW | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
3 sites, 56.1 MW: 39.1 MW connected, 17 MW accepted to connect
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Nevendon Grid 33kV | 1 | 4.6 MW | – | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 4.6 MW: 4.6 MW connected
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Nevendon Grid 33kV | 1 | 1.2 MW | – | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 1.2 MW: 1.2 MW connected
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Nevendon Grid 33kV | 6 | 53 MW | 7 MW | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
6 sites, 60 MW: 53 MW connected, 7 MW accepted to connect
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Abberton Grid 33kV | 3 | 9.1 MW | – | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
3 sites, 9.1 MW: 9.1 MW connected
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Abberton Grid 33kV | 4 | 44.8 MW | – | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
4 sites, 44.8 MW: 44.8 MW connected
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Rayleigh Local 33kV | 2 | – | 30 MW | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2 sites, 30 MW: 30 MW accepted to connect
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Southend Grid 33kV | 1 | 10 MW | – | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 10 MW: 10 MW connected
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Not stated | 11 | 260 MW | 459 MW | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11 sites, 719 MW: 260 MW connected, 459 MW accepted to connect
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Not found among the sites of 1 MW and over in UKPN’s November 2026 edition
2 sites last found at this grid supply point were not found among this edition’s sites of 1 MW and over by their MPAN, grid reference or name and postcode. QueueWatch keeps their pages for six months and does not say whether they have left the register.
- (ANM - N/A) Raymonds Farm last found in the October 2026 edition
- Church Lane last found in the September 2026 edition
What changed recently
Changes to sites here found in both editions of each pair, newest first.
October 2026 edition to November 2026 edition: 46 sites matched. 1 site at this grid supply point couldn’t be matched between the two editions, because its details changed or it appears in only one.
1 site without a match in the other edition
In the October 2026 edition only (1)
- (ANM - N/A) Raymonds FarmEastern Power Networks (EPN)Accepted to connect239.99 MW
- (ANM) ChelmsfordNovember 2026 editionTarget energisation date moved from 31 Dec 2028 to 11 Jan 2032 (36 months later)
- (ANM) Crows LaneNovember 2026 editionTarget energisation date moved from 31 Dec 2028 to 11 Jan 2032 (36 months later)
- (ANM) Marshes Burnham-On-CrouchNovember 2026 editionTarget energisation date moved from 31 Dec 2028 to 11 Jan 2032 (36 months later)
- (ANM) South Woodham FerrersNovember 2026 editionTarget energisation date moved from 31 Dec 2028 to 11 Jan 2032 (36 months later)
- Cards RoadNovember 2026 editionTarget energisation date moved from 6 Jan 2025 to 30 Mar 2026 (15 months later)
- Fambridge FarmNovember 2026 editionTarget energisation date moved from 6 Jan 2025 to 30 Mar 2026 (15 months later)
- Great Wheatley Solar FarmNovember 2026 editionTarget energisation date moved from 6 Jan 2025 to 30 Mar 2026 (15 months later)
- Rayleigh SiteNovember 2026 editionTarget energisation date moved from 6 Jan 2025 to 30 Mar 2026 (15 months later)
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?
How power reaches a site
A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.