Land Adjoining The Wallburys

IG Renewables Limited at Pelham

UKPN Embedded Capacity Register 2 – 1MW and above, October 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
Not stated
Status
Accepted to connect
Customer
IG Renewables Limited
Site name
Land Adjoining The Wallburys
Address
Land Lying To The West Of Great Hallingbury, Latchmore Bank, Bishops Stortford, Hertfordshire, CM22 7SQ
Grid reference
Easting 549176, northing 217932
Licence area
Eastern Power Networks (EPN)
Grid supply point
Pelham
Bulk supply point
Bishops Stortford Grid 33kV
Primary substation
Thorley Primary 11kV
Connection voltage
11 kV
Technology group
Solar
Energy source 1
Solar, Photovoltaic: 3.6 MW registered
Energy source 2
Stored Energy (all stored energy irrespective of the original energy source), Storage - Electrochemical (Batteries): 3.6 MW registered
Registered capacity
3.6 MW
Change to maximum export capacity
3.6 MW
Change to maximum import capacity
3.6 MW
Flexible connection
Yes
In a connection queue
Yes
Date accepted
16 Sep 2026
Date connected
Not stated
Distribution reinforcement reference
Not published by UKPN
Transmission reinforcement reference
Not published by UKPN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
14 Oct 2026
Tracked since
October 2026 edition

Change history

Tracked since the October 2026 edition.

Changes to the details QueueWatch tracks, newest first.

No changes to show: it has been found in one edition.

Also at Pelham

GSP view

39 other sites at this grid supply point in the October 2026 edition. In all, the sites here total 866 MW: 234 MW connected, 632 MW accepted to connect.

See all 39

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose