QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

(ANM) Links Rd

Links Solar Farm Limited at Braintree

UKPN Embedded Capacity Register 2 – 1MW and above, October 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Date connected
12 Jul 2024
Status
Connected
Customer
Links Solar Farm Limited
Site name
(ANM) Links Rd
Address
Braintree, Essex, CM77 8DS
Grid reference
Easting 580010, northing 221238
Licence area
Eastern Power Networks (EPN)
Grid supply point
Braintree
Bulk supply point
Braintree Local 33kV
Primary substation
Not stated
Connection voltage
33 kV
Technology group
Solar
Energy source 1
Solar, Photovoltaic: 26 MW registered
Registered capacity
26 MW
Maximum export capacity
26 MW
Maximum import capacity
0.5 MW
Flexible connection
Yes
In a connection queue
No
Date accepted
Not stated
Target energisation date
Not stated
Distribution reinforcement reference
Not published by UKPN
Transmission reinforcement reference
Not published by UKPN
Export MPAN
1050003008949
Import MPAN
Not stated
Last updated
14 Apr 2025
Tracked since
September 2026 edition

Change history

Tracked since the September 2026 edition, across 2 editions.

Changes to its status, capacity, technology or customer, newest first.

No change to its status, capacity, technology or customer.

Also at Braintree

GSP view

16 other sites at this grid supply point in the October 2026 edition. In all, the sites here total 215 MW: 159 MW connected, 56 MW accepted to connect.

See all 16

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose