QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Distribution / UKPN / Grid supply point

City Road

Grid supply point in London Power Networks (LPN)

UKPN Embedded Capacity Register 2 – 1MW and above, November 2026 edition

13sites of 1 MW and over
34.2 MWcapacity
34.2 MWconnected (13 sites)
–accepted to connect (0 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Gas and other fossil1334.2 MW34.2 MW–

Storage capacity in MWh: no site here states any.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the November 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
Finsbury Mkt F 33kV18.7 MW–
Finsbury Mkt F 33kV12.4 MW–
Bankside D 20kV24.3 MW–
Back Hill 33kV11.6 MW–
Not stated26.7 MW–
Not stated24.2 MW–
Not stated23.4 MW–
Not stated11.6 MW–
Not stated11.2 MW–

Search and filter all 13 sites at City Road

Not found among the sites of 1 MW and over in UKPN’s November 2026 edition

1 site last found at this grid supply point was not found among this edition’s sites of 1 MW and over by its MPAN, grid reference or name and postcode. QueueWatch keeps its page for six months and does not say whether it has left the register.

What changed recently

Changes to sites here found in both editions of each pair, newest first.

October 2026 edition to November 2026 edition: 13 sites matched. 1 site at this grid supply point couldn’t be matched between the two editions, because its details changed or it appears in only one.

1 site without a match in the other edition
In the October 2026 edition only (1)

No change to any detail QueueWatch tracks for these sites so far.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.