Distribution / UKPN / Grid supply point

Bramford

Grid supply point in Eastern Power Networks (EPN)

UKPN Embedded Capacity Register 2 – 1MW and above, November 2026 edition

110sites of 1 MW and over
2.3 GWcapacity
1.0 GWconnected (65 sites)
1.3 GWaccepted to connect (45 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Solar671.5 GW0.3 GW1.2 GW
Storage7300 MW140 MW160 MW
Wind9253 MW226 MW27 MW
Bioenergy and waste16165 MW165 MW–
Gas and other fossil11161 MW161 MW–

Storage capacity in MWh: no site here states any.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the November 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
Bury Grid 33kV1–29.6 MW
Bury Grid 33kV12.6 MW–
Bury Grid 33kV11.2 MW–
Bury Grid 33kV596 MW40 MW
Diss Grid 33kV1–29.6 MW
Diss Grid 33kV15 MW–
Diss Grid 33kV1–5 MW
Diss Grid 33kV22 MW–
Diss Grid 33kV11.5 MW–
Diss Grid 33kV684 MW30 MW
Halesworth Grid 33kV215.1 MW–
Halesworth Grid 33kV1–15 MW
Halesworth Grid 33kV626 MW94 MW
Clacton Grid 33kV727 MW105 MW
Stowmarket Grid 132/33kV2–120 MW
Thetford Grid 33kV1–19.8 MW
Thetford Grid 33kV23.9 MW–
Thetford Grid 33kV11 MW–
Thetford Grid 33kV592.1 MW–
Wickham Market Grid 33kV29.4 MW–
Wickham Market Grid 33kV11.1 MW–
Wickham Market Grid 33kV11 MW–
Wickham Market Grid 33kV415 MW65 MW
Lawford Grid 33kV663.4 MW17.6 MW
Ilketshall Grid 33kV39.2 MW–
Ilketshall Grid 33kV33 MW4 MW
Ilketshall Grid 33kV11 MW–
Ilketshall Grid 33kV333 MW29.6 MW
Wickham Market Grid 132/33kV2–70 MW
Diss Grid 132/33KV1–30 MW
Diss Grid 132/33KV1–20 MW
Diss Grid 132/33KV1–10 MW
Stowmarket Grid 33kV26.5 MW–
Stowmarket Grid 33kV225.5 MW20 MW
Diss Grid1–49.4 MW
Ipswich Grid1–35 MW
Thetford 132/33kV1–30 MW
Colchester Grid 33kV24.3 MW–
Colchester Grid 33kV221.5 MW–
Felixstowe Grid 33kV1–22.5 MW
Cliff Quay Grid 33kV14 MW–
Cliff Quay Grid 33kV12.4 MW–
Cliff Quay Grid 33kV11.2 MW–
Cliff Quay Grid 33kV110.9 MW–
Not stated18442 MW435 MW

Search and filter all 110 sites at Bramford

What changed recently

Changes to sites here found in both editions of each pair, newest first.

October 2026 edition to November 2026 edition: 110 sites matched. Every October site and every November site at this grid supply point had a match in the other edition.

No change to any detail QueueWatch tracks for these sites so far.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.