Distribution / UKPN / Grid supply point

Northfleet East

Grid supply point in South Eastern Power Networks (SPN)

UKPN Embedded Capacity Register 2 – 1MW and above, November 2026 edition

36sites of 1 MW and over
587 MWcapacity
188 MWconnected (21 sites)
399 MWaccepted to connect (15 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Solar18359 MW67 MW292 MW
Storage4127 MW42 MW85 MW
Gas and other fossil875.1 MW67.1 MW8 MW
Bioenergy and waste627 MW12.4 MW14.6 MW

Storage capacity in MWh: no site here states any.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the November 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
Northfleet East 33kV21.2 MW14.6 MW
Northfleet East 33kV17.5 MW–
Northfleet East 33kV1–7 MW
Northfleet East 33kV15.3 MW–
Northfleet East 33kV23.7 MW–
Northfleet East 33kV11.3 MW–
Northfleet East 33kV323.6 MW35 MW
Burham 33kV280.3 MW–
Pembury Grid 33kV24.8 MW–
Pembury Grid 33kV528.5 MW31.3 MW
Chelsfield Grid11.2 MW–
Chelsfield Grid1–45 MW
Dormansland Grid 33kV15 MW–
Dormansland Grid 33kV11.8 MW–
Dormansland Grid 33kV1–1 MW
Dormansland Grid 33kV116 MW–
Chelsfield Grid 33kV12.2 MW–
Chelsfield Grid 33kV1–17.5 MW
Pembury1–4.9 MW
Burham1–4 MW
Not stated66 MW239 MW

Search and filter all 36 sites at Northfleet East

Not found among the sites of 1 MW and over in UKPN’s November 2026 edition

2 sites last found at this grid supply point were not found among this edition’s sites of 1 MW and over by their MPAN, grid reference or name and postcode. QueueWatch keeps their pages for six months and does not say whether they have left the register.

What changed recently

Changes to sites here found in both editions of each pair, newest first.

October 2026 edition to November 2026 edition: 36 sites matched. 2 sites at this grid supply point couldn’t be matched between the two editions, because their details changed or they appear in only one.

2 sites without a match in the other edition
In the October 2026 edition only (2)
  • Postern ParkSouth Eastern Power Networks (SPN)Accepted to connect8 MW
  • Ridley Court FarmSouth Eastern Power Networks (SPN)Accepted to connect49.9 MW
  • Bockingfold FarmNovember 2026 editionTarget energisation date moved from 24 Apr 2025 to 11 Jul 2025 (3 months later)
  • Gabriel Spring RoadNovember 2026 editionTarget energisation date moved from 31 Jan 2025 to 31 Oct 2027 (33 months later)
  • Horton Wood Solar FarmNovember 2026 editionTarget energisation date moved from 31 Oct 2025 to 20 Jun 2026 (8 months later)
  • Isle Of GrainNovember 2026 editionTarget energisation date moved from 31 Dec 2024 to 31 Dec 2025 (12 months later)
  • Marden GenerationNovember 2026 editionTarget energisation date moved from 31 Mar 2025 to 9 Jan 2027 (21 months later)
  • Northfleet East GridNovember 2026 editionTarget energisation date moved from 30 Jun 2025 to 31 Oct 2025 (4 months later)
  • Westgate PowerOctober 2026 editionCapacity changed from 5.34 MW to 5.33 MW
  • Westgate PowerOctober 2026 editionExport capacity changed from 5.34 MW to 5.33 MW
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.