QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Distribution / UKPN / Grid supply point

Wimbledon 132kV 3 & 4

Grid supply point in London Power Networks (LPN)

UKPN Embedded Capacity Register 2 – 1MW and above, November 2026 edition

5sites of 1 MW and over
22 MWcapacity
22 MWconnected (5 sites)
–accepted to connect (0 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Gas and other fossil522 MW22 MW–

Storage capacity in MWh: no site here states any.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the November 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
Wimbledon Grid C 33kV12.1 MW–
Not stated315.9 MW–
Not stated14 MW–

Search and filter all 5 sites at Wimbledon 132kV 3 & 4

What changed recently

Changes to sites here found in both editions of each pair, newest first.

October 2026 edition to November 2026 edition: 5 sites matched. Every October site and every November site at this grid supply point had a match in the other edition.

No change to any detail QueueWatch tracks for these sites so far.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.