(ANM) Wales End Farm
Noventum Power Limited at Pelham
UKPN Embedded Capacity Register 2 – 1MW and above, October 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 31 Oct 2034
- Status
- Accepted to connect
- Customer
- Noventum Power Limited
- Site name
- (ANM) Wales End Farm
- Address
- Cavendish, Sudbury, Suffolk, CO10 8DE
- Grid reference
- Easting 579620, northing 249704
- Licence area
- Eastern Power Networks (EPN)
- Grid supply point
- Pelham
- Bulk supply point
- Belchamp Grid 33kV
- Primary substation
- Not stated
- Connection voltage
- 33 kV
- Technology group
- Solar
- Energy source 1
- Solar, Photovoltaic: 12.5 MW registered
- Registered capacity
- 12.5 MW
- Change to maximum export capacity
- 12.5 MW
- Change to maximum import capacity
- 0 MW
- Flexible connection
- Yes
- In a connection queue
- Yes
- Date accepted
- 10 Jun 2023
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by UKPN
- Transmission reinforcement reference
- Not published by UKPN
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 12 Jul 2024
- Tracked since
- September 2026 edition
Change history
Tracked since the September 2026 edition, across 2 editions.
Changes to its status, capacity, technology or customer, newest first.
No change to its status, capacity, technology or customer.
Also at Pelham
GSP view38 other sites at this grid supply point in the October 2026 edition. In all, the sites here total 863 MW: 234 MW connected, 629 MW accepted to connect.
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose