Distribution / UKPN / Grid supply point

Ninfield

Grid supply point in South Eastern Power Networks (SPN)

UKPN Embedded Capacity Register 2 – 1MW and above, November 2026 edition

33sites of 1 MW and over
823 MWcapacity
279 MWconnected (22 sites)
544 MWaccepted to connect (11 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Storage11623 MW99 MW524 MW
Solar1395.4 MW75 MW20.4 MW
Wind271.5 MW71.5 MW–
Bioenergy and waste630 MW30 MW–
Gas and other fossil14.1 MW4.1 MW–

Storage capacity in MWh: no site here states any.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the November 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
Lewes Grid 33kV1–5.5 MW
Lewes Grid 33kV25.2 MW–
Lewes Grid 33kV638.4 MW39.9 MW
Broad Oak 21–50 MW
Ninfield Grid 33kV33.8 MW–
Ninfield Grid 33kV12 MW–
Ninfield Grid 33kV323.6 MW–
Newhaven Grid 33kV121 MW–
Hartley Grid1–4.4 MW
Hartley Grid1–16 MW
Eastbourne Grid 33kV1–17 MW
Polegate Grid1–15 MW
Polegate Grid 33kV17 MW–
Polegate Grid 33kV17.5 MW–
Broad Oak Grid1–6.5 MW
Hartley Grid 33kV14 MW–
Not stated14.1 MW–
Not stated6163 MW390 MW

Search and filter all 33 sites at Ninfield

What changed recently

Changes to sites here found in both editions of each pair, newest first.

October 2026 edition to November 2026 edition: 33 sites matched. Every October site and every November site at this grid supply point had a match in the other edition.

  • Boreham StreetNovember 2026 editionTarget energisation date moved from 31 Jan 2029 to 31 Dec 2031 (35 months later)
  • Land At Priesthawes FarmNovember 2026 editionTarget energisation date moved from 31 Dec 2030 to 31 Dec 2031 (12 months later)
  • Mathurst Farm SolarNovember 2026 editionTarget energisation date moved from 31 Mar 2029 to 31 Dec 2031 (33 months later)
  • Olives FarmNovember 2026 editionTarget energisation date moved from 31 Dec 2030 to 31 Dec 2027 (36 months earlier)
  • Shearwater Solar FarmNovember 2026 editionTarget energisation date moved from 31 Jan 2029 to 31 Dec 2031 (35 months later)
  • Francis WoodOctober 2026 editionCapacity changed from 4.4 MW to 7 MW
  • Francis WoodOctober 2026 editionExport capacity changed from 4.4 MW to 7 MW
  • Olives FarmOctober 2026 editionCapacity changed from 75 MW to 49.9 MW
  • Olives FarmOctober 2026 editionExport capacity changed from 75 MW to 49.9 MW
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.