QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

(ANM) Tooleys Farm

Gridsource at Pelham

UKPN Embedded Capacity Register 2 – 1MW and above, October 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
31 Oct 2034
Status
Accepted to connect
Customer
Gridsource
Site name
(ANM) Tooleys Farm
Address
Great Dunmow, Essex, CM6 3AA
Grid reference
Easting 564460, northing 222720
Licence area
Eastern Power Networks (EPN)
Grid supply point
Pelham
Bulk supply point
Thaxted Grid 33kV
Primary substation
Not stated
Connection voltage
33 kV
Technology group
Solar
Energy source 1
Solar, Photovoltaic: 12 MW registered
Registered capacity
12 MW
Change to maximum export capacity
12 MW
Change to maximum import capacity
0.8 MW
Flexible connection
Yes
In a connection queue
Yes
Date accepted
11 Mar 2023
Date connected
Not stated
Distribution reinforcement reference
Not published by UKPN
Transmission reinforcement reference
Not published by UKPN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
12 Jul 2024
Tracked since
September 2026 edition

Change history

Tracked since the September 2026 edition, across 2 editions.

Changes to its status, capacity, technology or customer, newest first.

No change to its status, capacity, technology or customer.

Also at Pelham

GSP view

38 other sites at this grid supply point in the October 2026 edition. In all, the sites here total 863 MW: 234 MW connected, 629 MW accepted to connect.

See all 38

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose