QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

Projects in the TEC register

Every transmission-connected and large embedded project in the 1 Oct 2026 register, one row per project. Filter to see who is queued where, and when.

2,054 projects 596.8 GW queued, 15 GW of it with Gate 2 offers
Bute Hydrogen Project 1HALDANE ENERGY PROJECT 1 LIMITEDThermal (gas, biomass, waste)England and Wales4,80031 Oct 2035Gate 1ScopingNo source matched
Drax BECCSDrax Power LimitedThermal (gas, biomass, waste)England and Wales3,90630 Oct 2035Not statedScopingNo source matched
Bute Hydrogen Project 2HALDANE ENERGY PROJECT 2 LIMITEDThermal (gas, biomass, waste)England and Wales3,60031 Oct 2035Gate 1ScopingNo source matched
Bute Hydrogen Project 3HALDANE ENERGY PROJECT 3 LIMITEDThermal (gas, biomass, waste)England and Wales3,60031 Oct 2035Gate 1ScopingNo source matched
Bute Hydrogen Project 5HALDANE ENERGY PROJECT 5 LIMITEDThermal (gas, biomass, waste)England and Wales3,60031 Oct 2035Gate 1ScopingNo source matched
Bute Hydrogen Project 6Haldane Energy Project 6 LimitedThermal (gas, biomass, waste)England and Wales3,60031 Oct 2037Gate 1ScopingNo source matched
Hinkley Point CNNB GENERATION COMPANY (HPC) LIMITEDNuclearEngland and Wales3,34031 Mar 2029Not statedScopingGranted
Sizewell CSizewell C LimitedNuclearEngland and Wales3,34031 Jul 2035Not statedConsents ApprovedGranted
Hornsea Power Station 3HORNSEA PROJECT THREE (UK) LIMITEDOffshore windEngland and Wales3,0001 Oct 2026Not statedConsents ApprovedGranted
Marram Wind Offshore Wind FarmMarramwind LimitedOffshore windNorth Scotland3,00031 Oct 2031Not statedScopingAwaiting decision
Hornsea Power Station 4ORSTED HORNSEA PROJECT FOUR LIMITEDOffshore windEngland and Wales2,60030 Oct 2028Not statedScopingGranted
PortwindSE PORTWIND LTDOffshore windEngland and Wales2,5006 Dec 2036Gate 1ScopingNo source matched
Eggborough CCGT - OCGT - BESSEGGBOROUGH POWER LIMITEDThermal (gas, biomass, waste)England and Wales2,4501 Oct 2026Not statedAwaiting ConsentsGranted
Bute Hydrogen Project 4HALDANE ENERGY PROJECT 4 LIMITEDThermal (gas, biomass, waste)England and Wales2,40031 Oct 2035Gate 1ScopingNo source matched
Bute Hydrogen Project 7.1HALDANE ENERGY PROJECT 7 LIMITEDStorageEngland and Wales2,40031 Oct 2038Gate 1ScopingNo source matched
OWPL WindfarmOFFSHORE WIND POWER LIMITEDOffshore windNorth Scotland2,25031 Dec 2029Not statedScopingNo source matched
East Claydon Green Energy CentreEAST CLAYDON GREEN NG LIMITEDStorage with solar or windEngland and Wales2,0501 Oct 2034Not statedAwaiting ConsentsNo source matched
Caledonia Offshore Wind FarmCALEDONIA OFFSHORE WIND FARM LIMITEDOffshore windNorth Scotland2,00031 Mar 2031Not statedScopingNo source matched
GallosCorio Generation LimitedOffshore windEngland and Wales2,0006 Dec 2036Not statedScopingNo source matched
Machair Offshore Wind FarmSCOTTISHPOWER RENEWABLES (UK) LIMITEDOffshore windSouth Scotland2,00016 Sep 2033Not statedScopingAwaiting decision
Walpole Flexible GenerationFLEXIBLE GENERATION 1 LTDThermal (gas, biomass, waste)England and Wales2,00030 Jun 2033Not statedScopingNo source matched
ARVEN OFFSHORE WIND FARMARVEN OFFSHORE WIND FARM LIMITEDOffshore windNorth Scotland1,80031 Oct 2033Not statedScopingNo source matched
Bellrock Offshore Wind FarmBellrock Offshore Wind Farm LimitedOffshore windNorth Scotland1,80031 Oct 2032Not statedScopingAwaiting decision
Berwick Bank Offshore Wind Farm CBERWICK BANK C LIMITEDOffshore windEngland and Wales1,80030 Nov 2029Not statedScopingNo source matched
Carrington Lane BESSApatura Battery LtdStorageEngland and Wales1,80030 Oct 2037Gate 1ScopingNo source matched
Damhead Creek 2VPI Power LimitedThermal (gas, biomass, waste)England and Wales1,80031 Oct 2030Not statedConsents ApprovedNo source matched
Earba PSHEARBA LIMITEDHydro & marineNorth Scotland1,80031 Dec 2032Not statedConsents ApprovedNo source matched
Glen Earrach PSHGLEN EARRACH ENERGY LIMITEDHydro & marineNorth Scotland1,80031 Oct 2035Not statedScopingNo source matched
North-East Offshore Hybrid AssetNational Grid Interconnector Holdings LimitedOffshore windNorth Scotland1,80030 Jun 2037Gate 1ScopingNo source matched
NatPower Enderby - Patford Bridge Green Energy ParkENDERBY ENERGY LIMITEDStorageEngland and Wales1,79930 Oct 2037Gate 1ScopingNo source matched
SpringwellSPRINGWELL ENERGYFARM LIMITEDStorage with solar or windEngland and Wales1,60030 Oct 2029Not statedScopingGranted
GT R4 Offshore Wind FarmGT R4 LIMITEDOffshore windEngland and Wales1,50030 Nov 2030Not statedScopingNo source matched
HavbredeyHAVBREDEY LIMITEDOffshore windNorth Scotland1,50031 Oct 2033Gate 1ScopingNo source matched
Mablethorpe StorageTHEDDLETHORPE FLEXIBLE GENERATION LIMITEDThermal (gas, biomass, waste)England and Wales1,50030 Nov 2031Not statedScopingNo source matched
Merlin 2 Offshore WindfarmOFFSHORE WIND LIMITEDOffshore windEngland and Wales1,50031 Oct 2031Gate 1ScopingNo source matched
Mona Offshore Wind FarmMona Offshore Wind LimitedOffshore windEngland and Wales1,50031 Oct 2029Not statedScopingGranted
Morgan Offshore Wind FarmMorgan Offshore Wind LimitedOffshore windEngland and Wales1,50030 Nov 2029Not statedScopingGranted
Morven A Offshore Wind Farm (Prev Phoenix 1A)Morven Offshore Wind LimitedOffshore windEngland and Wales1,50031 Oct 2031Not statedScopingNo source matched
Nursling Flexible GenerationSOUTH ENG FLEXIBLE GENERATION LIMITEDThermal (gas, biomass, waste)England and Wales1,50030 Oct 2038Not statedScopingNo source matched
Old Flatts FarmNet Zero One LtdStorage with solar or windEngland and Wales1,50030 Oct 2029Not statedScopingNo source matched
Phoenix 1B Offshore Wind FarmMorven Offshore Wind LimitedOffshore windSouth Scotland1,50031 Oct 2033Not statedScopingNo source matched
SSE Celtic Sea 1SSE RENEWABLES OFFSHORE WINDFARM HOLDINGS LIMITEDOffshore windEngland and Wales1,5006 Dec 2036Not statedScopingNo source matched
Stromar Offshore WindfarmStromar Offshore Wind Farm LimitedOffshore windNorth Scotland1,50031 Oct 2033Not statedScopingNo source matched
Torridge Offshore Wind FarmGWYNT GLAS OFFSHORE WIND FARM LIMITEDOffshore windEngland and Wales1,50031 Oct 2031Gate 1ScopingNo source matched
Fearna PSH 2FEARNA PSH LIMITEDHydro & marineNorth Scotland1,49511 Nov 2036Not statedAwaiting ConsentsNo source matched
Dogger Bank D Offshore Wind FarmDoggerbank Offshore Wind Farm Project 4 Projco LimitedOffshore windEngland and Wales1,45031 Oct 2031Not statedScopingNo source matched
Dogger Bank South EastRWE Renewables UK Dogger Bank South (East) LimitedOffshore windEngland and Wales1,45030 Oct 2030Not statedScopingNo source matched
Dogger Bank South WestRWE RENEWABLES UK DOGGER BANK SOUTH (WEST) LIMITEDOffshore windEngland and Wales1,45030 Oct 2030Not statedScopingNo source matched
Ferrybridge DKeadby Generation LimitedThermal (gas, biomass, waste)England and Wales1,4204 Oct 2030Not statedScopingNo source matched
INTOG 2CERULEAN WINDS LIMITEDOffshore windSouth Scotland1,40030 Jun 2032Not statedScopingNo source matched
Overton Solar & Storage FarmELEMENTS GREEN LIMITEDStorage with solar or windEngland and Wales1,4001 Jun 2032Not statedScopingNo source matched
Tealing Energy ParkONPATH ENERGY LIMITEDStorageNorth Scotland1,40031 Oct 2033Gate 1ScopingNo source matched
Thorpe Marsh Energy ParkTHORPE MARSH GREEN ENERGY HUB LIMITEDStorageEngland and Wales1,40030 Jan 2027Gate 2Under Construction/CommissioningGranted
Trafford 2 BESSFUTURE POINT MANCHESTER LIMITEDStorageEngland and Wales1,40030 Oct 2038Not statedScopingNo source matched
Berwick Bank Offshore Wind Farm ABERWICK BANK A LIMITEDOffshore windSouth Scotland1,38031 Oct 2028Not statedScopingNo source matched
Berwick Bank Offshore Wind Farm BBerwick Bank B LimitedOffshore windSouth Scotland1,38031 Oct 2029Not statedScopingNo source matched
CENOSFLOTATION ENERGY LIMITEDOffshore windNorth Scotland1,35031 Oct 2035Not statedScopingAwaiting decision
Scira-Dudgeon ExtensionSHERINGHAM SHOAL AND DUDGEON EXTENSIONS PROJCO LIMITEDOffshore windEngland and Wales1,3501 Jan 2030Not statedScopingNo source matched
NatPower Kinoulton Green Energy ParkDALBY ENERGY LIMITEDStorageEngland and Wales1,33031 Dec 2034Gate 1ScopingNo source matched
Isle of Man Offshore Wind FarmMooir Vannin Offshore Wind Farm LimitedOffshore windEngland and Wales1,32030 Oct 2037Gate 1ScopingNo source matched
Norfolk BoreasNORFOLK BOREAS LIMITEDOffshore windEngland and Wales1,3201 Oct 2029Not statedAwaiting ConsentsGranted
Ossian 1 Offshore Wind FarmOssian Offshore Wind Farm LimitedOffshore windNorth Scotland1,32031 Oct 2033Not statedScopingNo source matched
VanguardNORFOLK VANGUARD WEST LIMITEDOffshore windEngland and Wales1,3201 Dec 2025 Past dateNot statedConsents ApprovedGranted
Vanguard EastNorfolk Vanguard East LtdOffshore windEngland and Wales1,3201 Apr 2028Not statedScopingNo source matched
East Anglia ThreeEAST ANGLIA THREE LIMITEDOffshore windEngland and Wales1,30031 Jan 2026 Past dateNot statedConsents ApprovedGranted
Coire Glas Pumped StorageCOIRE GLAS HYDRO PUMPED STORAGE LIMITEDHydro & marineNorth Scotland1,29631 Oct 2029Not statedConsents ApprovedNo source matched
Little Horsted Energy ParkELEMENTS GREEN DEVELOPMENT LTDStorage with solar or windEngland and Wales1,26031 Oct 2037Not statedScopingNo source matched
Cold NortonBSR APPLICATIONS LIMITEDStorage with solar or windEngland and Wales1,25031 Oct 2036Gate 1ScopingNo source matched
Dogger Bank Project CDOGGERBANK OFFSHORE WIND FARM PROJECT 3 PROJCO LIMITEDOffshore windEngland and Wales1,2001 Apr 2025 Past dateNot statedConsents ApprovedNo source matched
Legacy Green Energy CentreLEGACY GREEN ENERGY LIMITEDStorageEngland and Wales1,20030 Oct 2027Gate 1Awaiting ConsentsNo source matched
Rampion Extension Offshore Wind FarmRAMPION EXTENSION DEVELOPMENT LIMITEDOffshore windEngland and Wales1,20031 Dec 2029+41 moNot statedScopingGranted
The BeaconBeacon Solar LimitedStorage with solar or windEngland and Wales1,20031 Oct 2037Gate 1ScopingNo source matched
Vicarage Drove BESSUK Transition Power Holdings LimitedStorageEngland and Wales1,20030 Oct 2034Gate 1ScopingNo source matched
Awel Y MorAWEL Y MOR OFFSHORE WIND FARM LIMITEDOffshore windEngland and Wales1,1001 Mar 2030Not statedScopingGranted
Five Estuaries Offshore Wind FarmFIVE ESTUARIES OFFSHORE WIND FARM LIMITEDOffshore windEngland and Wales1,08031 Oct 2030Not statedScopingGranted
Bradwell Energy ParkLOW CARBON SOLAR PARK 28 LIMITEDStorage with solar or windEngland and Wales1,05031 Oct 2032Not statedScopingNo source matched
Butlers Wood Green Energy CentreBUTLERS WOOD NG LIMITEDStorage with solar or windEngland and Wales1,02530 Oct 2031Not statedAwaiting ConsentsNo source matched
Cilfynydd Green Energy CentreCILFYNYDD NG LIMITEDStorage with solar or windEngland and Wales1,02530 Oct 2029+12 moGate 1Awaiting ConsentsNo source matched
Drakelow Green Energy CentreDRAKELOW NG LIMITEDStorage with solar or windEngland and Wales1,02530 Apr 2028Not statedAwaiting ConsentsNo source matched
Enderby Green Energy CentreENDERBY BESS LIMITEDStorage with solar or windEngland and Wales1,02530 Oct 2028Not statedAwaiting ConsentsNo source matched
Feckenham Green Energy CentreFECKENHAM GREEN NG LIMITEDStorage with solar or windEngland and Wales1,02530 Oct 2032Not statedScopingNo source matched
Hams Hall Green Energy CentreHAMS HALL NG LIMITEDStorage with solar or windEngland and Wales1,02530 Oct 2028Gate 1ScopingNo source matched
Harker Green Energy CentreBlackdyke BESS LimitedStorage with solar or windEngland and Wales1,02530 Oct 2028Not statedAwaiting ConsentsNo source matched
Hawthorn Pit Green Energy CentreHAWTHORN PIT NG LIMITEDStorage with solar or windEngland and Wales1,02531 Oct 2032Not statedAwaiting ConsentsNo source matched
Mablethorpe Green Energy CentreMABLETHORPE NG LIMITEDStorage with solar or windEngland and Wales1,02530 Oct 2033Gate 1Awaiting ConsentsNo source matched
Overton Green Energy CentreOVERTON NG LIMITEDStorage with solar or windEngland and Wales1,02524 Oct 2035Not statedAwaiting ConsentsNo source matched
Pentir Green Energy CentreINNOVA RENEWABLES LIMITEDStorage with solar or windEngland and Wales1,02531 Oct 2037Gate 1Awaiting ConsentsNo source matched
Swansea North Green Energy CentreSWANSEA NORTH GREEN NG LIMITEDStorage with solar or windEngland and Wales1,02530 Oct 2028Not statedScopingNo source matched
Thorpe Marsh Green Energy CentreTHORPE MARSH NG LTDStorage with solar or windEngland and Wales1,02530 Oct 2030Not statedAwaiting ConsentsNo source matched
Willington Green Energy CentreWILLINGTON NG LIMITEDStorage with solar or windEngland and Wales1,02530 Oct 2028Not statedScopingNo source matched
Ayre (ex Cluaran Ear - Thuath) Offshore Wind FarmAYRE OFFSHORE WIND FARM LIMITEDOffshore windNorth Scotland1,00831 Oct 2033Not statedAwaiting ConsentsNo source matched
Bowdun (ex Cluaran Deas Ear) Offshore Wind FarmBOWDUN OFFSHORE WIND FARM LIMITEDOffshore windNorth Scotland1,00831 Dec 2035Not statedAwaiting ConsentsNo source matched
Cormoran Offshore Wind FarmSouth West Wind Holdco LimitedOffshore windEngland and Wales1,0086 Dec 2036Not statedScopingNo source matched
Mererid Offshore Wind FarmSouth West Wind Holdco LimitedOffshore windEngland and Wales1,0086 Dec 2036Not statedScopingNo source matched
Ossian 4 Offshore Wind FarmOssian Offshore Wind Farm LimitedOffshore windEngland and Wales1,00831 Oct 2033Not statedScopingNo source matched
Halfway Energy ParkDALRIADA RENEWABLES LIMITEDStorage with solar or windNorth Scotland1,00031 Oct 2035Not statedScopingNo source matched
Alcemi Bramford Battery Energy Storage Facility Phase 2ALCEMI STORAGE DEVELOPMENTS 1 LIMITEDStorageEngland and Wales1,00031 Oct 2034Gate 1ScopingNo source matched
Alverdiscott FarmAlverdiscott 10 Renewables LtdStorage with solar or windEngland and Wales1,00024 Apr 2037Not statedScopingNo source matched
Amersham MainAmersham 10 Renewables LimitedStorage with solar or windEngland and Wales1,00031 Oct 2037Not statedScopingNo source matched
BF88 OakleyBLUEFIELD RENEWABLE DEVELOPMENTS LIMITEDStorage with solar or windEngland and Wales1,0001 Nov 2038Not statedScopingNo source matched

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO

Planning

The planning decision or stage QueueWatch has for each project: from the Planning Inspectorate’s list of National Infrastructure Projects or DESNZ’s Renewable Energy Planning Database (REPD), July 2026 edition, where QueueWatch matched the project to a record, or read on the Planning Inspectorate’s page for the project.

“No source matched” means QueueWatch has not matched the project to a record in either source. It does not mean the project has no planning permission.

NESO’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.