QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Projects / England and Wales
Connection date
30 Oct 2028
Gate
Gate 1
Status
Scoping
Technology
Demand + Storage + Solar
Total capacity
1,025 MW
Connected now
0 MW
Still to connect
1,025 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-001765
Tracked since
14 Aug 2026

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
1040040030 Oct 2028Gate 1Scoping
206251,02531 Oct 2032Gate 1Scoping

Change history

Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.

No changes since 14 Aug 2026. Follow this project to see the next one on your watchlist.

Also queued at Hams Hall 400kV Substation

Substation view

1 other project, 1.4 GW still to connect at this substation in total.