Hams Hall Green Energy Centre
- Connection date
- 30 Oct 2028
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Demand + Storage + Solar
- Total capacity
- 1,025 MW
- Connected now
- 0 MW
- Still to connect
- 1,025 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001765
- In the register since
- February 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 400 | 400 | 30 Oct 2028 | Gate 1 | Scoping |
| 2 | 0 | 625 | 1,025 | 31 Oct 2032 | Gate 1 | Scoping |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Oct 2026 registerStage 1: Connection date moved from 31 Oct 2028 to 30 Oct 2028 (1 day earlier)
- 10 Oct 2026 registerStage 1: Connection date moved from 30 Oct 2028 to 31 Oct 2028 (1 day later)
- 23 Dec 2025 registerStage 1: Marked as Gate 1
- 16 Dec 2025 registerStage 2: Marked as Gate 1
- 21 Nov 2025 registerCustomer changed from HAMS HALL GREEN ENERGY LIMITED to HAMS HALL NG LIMITED
- 30 Sep 2025 registerStage removed (0 MW from 31 Oct 2037)
- 29 Jul 2025 registerNew stage added (0 MW from 31 Oct 2037)
- 27 Jun 2025 registerStage 1: Technology changed from Storage, Solar to Demand, Storage, Solar
- 27 Jun 2025 registerStage 2: Technology changed from Storage, Solar to Demand, Storage, Solar
- 29 Apr 2025 registerCustomer changed from HAMS HALL NG LIMITED to HAMS HALL GREEN ENERGY LIMITED
- 28 Mar 2025 registerCustomer changed from HAMS HALL GREEN ENERGY LIMITED to HAMS HALL NG LIMITED
- 28 Jul 2023 registerNew stage added (625 MW from 31 Oct 2032)
- 29 Jul 2022 registerConnection point changed from Ham Hall 400Kv to Hams Hall 400kV Substation
- 25 Feb 2022 registerAdded to the register
Also at Hams Hall 400kV Substation
Substation view1 other project, 1.1 GW still to connect at this substation in total.