Hams Hall Green Energy Centre
- Connection date
- 30 Oct 2028
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Demand + Storage + Solar
- Total capacity
- 1,025 MW
- Connected now
- 0 MW
- Still to connect
- 1,025 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001765
- Tracked since
- 14 Aug 2026
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 400 | 400 | 30 Oct 2028 | Gate 1 | Scoping |
| 2 | 0 | 625 | 1,025 | 31 Oct 2032 | Gate 1 | Scoping |
Change history
Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.
No changes since 14 Aug 2026. Follow this project to see the next one on your watchlist.
Also queued at Hams Hall 400kV Substation
Substation view1 other project, 1.4 GW still to connect at this substation in total.