Isle of Man Offshore Wind Farm
Mooir Vannin Offshore Wind Farm Limited at IMW01 OFFSHORE 275/66KV OFFSHORE SUBSTATION
- Connection date
- 30 Sep 2037 −1 month since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Offshore wind
- Total capacity
- 1,320 MW
- Connected now
- 0 MW
- Still to connect
- 1,320 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003698
- In the register since
- May 2023
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Oct 2026 registerConnection date moved from 30 Jul 2037 to 30 Sep 2037 (+2 months)
- 10 Oct 2026 registerConnection date moved from 30 Oct 2037 to 30 Jul 2037 (−3 months)
- 12 Jun 2026 registerConnection point changed from Penwortham 400kV Substation to IMW01 OFFSHORE 275/66KV OFFSHORE SUBSTATION
- 12 Jun 2026 registerMarked as Gate 1
- 26 Nov 2024 registerCustomer changed from Orsted Isle of Man (UK) Limited to Mooir Vannin Offshore Wind Farm Limited
- 30 May 2023 registerAdded to the register
Also at IMW01 OFFSHORE 275/66KV OFFSHORE SUBSTATION
Substation viewNo other projects in the register at this connection point.