Scira-Dudgeon Extension
SHERINGHAM SHOAL AND DUDGEON EXTENSIONS PROJCO LIMITED at Norwich Main 400kV Substation
- Connection date
- 1 Jan 2030
- Gate
- Not stated
- Status
- Scoping
- Technology
- Offshore wind
- Total capacity
- 1,350 MW
- Connected now
- 0 MW
- Still to connect
- 1,350 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000507
- In the register since
- January 2021 or earlier
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 719 | 719 | 1 Jan 2030 | Not stated | Scoping |
| 2 | 0 | 231 | 950 | 31 Oct 2031 | Not stated | Scoping |
| 3 | 0 | 400 | 1,350 | 1 Oct 2034 | Not stated | Scoping |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerCustomer changed from EQUINOR NEW ENERGY LIMITED to SHERINGHAM SHOAL AND DUDGEON EXTENSIONS PROJCO LIMITED
- 31 Jan 2025 registerStage 1: Connection date moved from 1 Jan 2029 to 1 Jan 2030 (+12 months)
- 27 Feb 2024 registerStage 1: Connection date moved from 1 Jul 2027 to 1 Jan 2029 (+18 months)
- 27 Feb 2024 registerNew stage added (400 MW from 1 Oct 2034)
- 31 Mar 2023 registerRenamed from Equinor
- 31 Mar 2023 registerNew stage added (231 MW from 31 Oct 2031)
- 23 Dec 2022 registerConnection point changed from Scira-Dudgeon Extension 220/66kV Offshore Substation to Norwich Main 400kV Substation
- 31 May 2022 registerConnection date moved from 1 Sep 2025 to 1 Jul 2027 (+22 months)
- 26 Feb 2021 registerConnection date moved from 9 Jan 2025 to 1 Sep 2025 (+8 months)
Also at Norwich Main 400kV Substation
Substation view3 other projects, 4.4 GW still to connect at this substation in total. 3.1 GW is due to connect here before this project’s connection date of 1 Jan 2030.