QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / North Scotland
Connection date
31 Oct 2035
Gate
Not stated
Status
Scoping
Planning consent
Application submitted 31 Jan 2025
Marine Scotland, reference 25995 · Source: REPD
Technology
Demand + Offshore wind
Total capacity
1,350 MW
Connected now
0 MW
Still to connect
1,350 MW
Transmission owner
SSEN Transmission (SHET)
Agreement type
Direct Connection
Region
North Scotland
Project number
PRO-001847
In the register since
July 2022

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 27 Jun 2025 register
    Connection point changed from Lackenby GSP to Peterhead 400kV Substation
  • 27 Jun 2025 register
    Capacity changed from 1,500 MW to 1,350 MW
  • 27 Jun 2025 register
    Connection date moved from 30 Oct 2033 to 31 Oct 2035 (+24 months)
  • 27 Jun 2025 register
    Transmission owner changed from NGET to SHET
  • 29 Oct 2024 register
    Customer changed from FLOTATION ENERGY PLC to FLOTATION ENERGY LIMITED
  • 31 Jan 2023 register
    Customer changed from FLOTATION ENERGY LIMITED to FLOTATION ENERGY PLC
  • 23 Dec 2022 register
    Customer changed from FLOTATION ENERGY PLC to FLOTATION ENERGY LIMITED
  • 23 Dec 2022 register
    Substation name updated in the register (from Lackenby to Lackenby GSP)
  • 29 Jul 2022 register
    Added to the register

Also at Peterhead 400kV Substation

Substation view

3 other projects, 3.1 GW still to connect at this substation in total. 1.8 GW is due to connect here before this project’s connection date of 31 Oct 2035.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO

Planning consent

The planning decision or stage for this project, from DESNZ’s Renewable Energy Planning Database (REPD), July 2026 edition, with the planning authority and its reference. QueueWatch matched the project to that record. NESO’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.