Rampion Extension Offshore Wind Farm
RAMPION EXTENSION DEVELOPMENT LIMITED at Bolney 400kV Substation
- Connection date
- 31 Dec 2029 +41 months since 9 Dec
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Granted 4 Apr 2025
The Planning Inspectorate - National Infrastructure, reference EN010117 · Source: REPD - Technology
- Offshore wind
- Total capacity
- 1,200 MW
- Connected now
- 0 MW
- Still to connect
- 1,200 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000467
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 4 Sep 2026 registerConnection date moved from 1 Aug 2026 to 31 Dec 2029 (+41 months)
- 29 Aug 2025 registerConnection point changed from Rampion Offshore Wind Farm to Bolney 400kV Substation
- 31 Dec 2021 registerCustomer changed from RWE RENEWABLES UK LIMITED to Rampion Extension Development Limited
- 26 Feb 2021 registerConnection date moved from 8 Jan 2026 to 1 Aug 2026 (+7 months)
Also at Bolney 400kV Substation
Substation view5 other projects, 1.5 GW still to connect at this substation in total. 57 MW is due to connect here before this project’s connection date of 31 Dec 2029.
- Bolney (tertiary)BOLNEY GREEN LIMITED, Storage with solar or wind, Gate 1May 202857 MW
- BolneyPIVOTED POWER LLP, Storage with solar or wind, Not statedJan 203147.5 MW
- Bolney Grid Stability ServicesWP GRID SERVICES 13 LIMITED, Other, Not statedOct 20310 MW
- Bolney FarmDragon Green 2 Renewables Ltd, Storage with solar or wind, Gate 1Oct 2037200 MW
- ShorehamVPI Power Limited, Thermal (gas, biomass, waste), Not statedConnected460 MW