Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Do projects connect on time?

Every project in NESO’s TEC register has a connection date: the date it’s due to connect. Many projects connect in stages, parts of their capacity each with its own connection date, so we look at each stage. This page compares each stage’s connection date in the register with when it connected, and counts the projects past their connection date today. For how often connection dates move while projects are still waiting, see Delays and exits. The figures on this page update with each new register.

Who this page helps, and how

Developers and investors. A project’s connection date in the register is when it’s due to connect, not when it will. See how late stages have connected after it, and build that into your programme and model.

Landowners. Check how late connections have come before you agree or extend a longstop date.

Power buyers and data centre tenants. Use the lateness by technology to set start dates you can rely on.

NESO and Ofgem. Watch the share connecting on time as the reformed queue’s connection dates come due.

1. Is the register slow to show a stage connected?

NESO’s register shows a stage connected when it records the stage’s MW connected, which can be after the stage first exports. To check, we compared the first connections of the 28 projects whose operational date we can find in DESNZ’s Renewable Energy Planning Database (REPD). The register first showed them connected a median of 2 months after that date, the middle half from 4 months before it to 6 months after it. The next section gives both readings, register only and with REPD dates, and they barely differ: projects really do connect late. It isn’t the register being slow to record them.

2 monthsmedian lag behind the REPD’s operational date
28 stagesmatched to the REPD

How long after the REPD’s operational date the register first showed the stage connected

Stages that were their project’s first connection, matched to the REPD. Press a bar to list its stages.

Within a monthMore than a month either way
How long after the REPD’s operational date the register first showed each stage connected
Months afterStages
Register more than a month before the REPD9
Within a month3
2 to 6 months after9
7 to 12 months after3
13 months or more after4
How we measured it

The REPD is DESNZ’s database of renewable and storage projects of 150 kW and over; its operational date is the date it gives a project as operational. Each stage is matched through the approved planning matches that put REPD facts on project pages, and only a project’s first connection is compared, as a record’s date is for the project. For the months up to October 2025 we hold one register a month, so for those stages the register can show a connection up to a month after it happened.

2. How late have stages connected against their connection date in the register?

Since February 2021, NESO’s TEC register has shown 109 stages connected, 18.6 GW at 105 projects, each connected as the register first shows it. Most of those we can compare connected later than their connection date in the register.

75 of 81connected late against their connection date in the register a year before
15 monthsthe median lateness

Of the 81 stages with a connection date in the register a year before they connected, as the register first shows it, 75 connected more than a month after it, by a median of 15 months, and a quarter of those by 25 months or more. 3 connected on time and 3 early. Against their connection date three years before, 44 of 45 were late, by a median of 24 months.

How late stages connected, against their connection date in the register a year before

Each stage’s own connection date in the last register at least 12 months before it connected. Press a bar to list its stages.

EarlyOn timeLate
How late stages connected, against their connection date in the register
Against their connection dateStagesOn timeLateEarlyMedian months late (quartiles)
12 months before81375315 (12 to 25)
24 months before67164221 (15 to 26)
36 months before45144024 (18 to 27)
in their first register103494522 (11 to 33)
in the register just before97787310 (6 to 21)
Against their connection date in the register a year before, by technology
TechnologyStagesOn timeLateEarlyMedian months late
Storage42140117
Solar101019
Onshore wind17215012
Offshore wind606027
Thermal604221
Hybrid707014
Other20206
Against their connection date in the register a year before, by the year they connected
YearStagesOn timeShare on timeLateEarlyMedian months late
20226233.3%406
20231200.0%12014
2024900.0%9014
20253600.0%33321
2026 so far1815.6%17015

What it means: Plan for a connection later than its connection date in the register.

How we measured it

A stage’s connection date in the register is its own row’s connection date (MW Effective From) in the last register at least 12, 24 or 36 months before it connected, in the first register that gave the row a connection date, and in the register just before it connected. On time is within a month either way, in whole months; late and early are beyond that. A stage that connected in steps counts once, at its first; a stage whose row wasn’t in the register at a point has no figure there, which is why fewer stages have a connection date further back.

The With REPD dates reading covers 3 fewer stages. By the REPD’s dates, Hawkers Hill Energy Park, Broadditch BESS and Chapel Farm Battery Storage Project connected within a year of first appearing in the register, so there’s no register from a year earlier to compare them with.

3. How many projects are past their connection date today?

On 3 November 2026, 101 projects had stages past their connection date, 16.9 GW of the 606.3 GW still to connect. 23 of them have been past it for two years or more.

101 projectswith stages past their connection date
16.9 GWof stages past their connection date

Stages past their connection date

Each project by how long its oldest stage still to connect has been past its connection date, in GW. Press a bar to list its projects.

GW past its connection date
Projects with stages past their connection date, by technology
TechnologyProjectsMW past its connection dateMW still to connect
Storage484,685.955,141.05
Solar1129.80129.80
Onshore wind171,286.891,443.99
Offshore wind55,850.006,600.00
Thermal94,020.004,531.00
Hybrid21963.191,033.60
All technologies10116,935.8318,879.44
How we measured it

A stage is past its connection date where it still has MW to connect and its own connection date is before the latest register. The register leaves a connection date that has passed standing until the stage connects or NESO gives it a new one.

What if your connection date is pushed back?

QueueQuant values your project across thousands of possible futures for its connection date and the market, and tells you whether to hold, cut MW, sell or walk away, and what would change that answer.

Price my projectSee use cases

How to cite this page

You’re welcome to quote our figures, charts and findings with this credit:

QueueWatch by QueueQuant, ‘Do projects connect on time?’, queuequant.com/queuewatch/connecting-on-time/ (data to 3 November 2026). Contains data from NESO’s TEC register. Supported by National Energy SO Open Data. Contains data from DESNZ’s Renewable Energy Planning Database. Contains public sector information licensed under the Open Government Licence v3.0.

Supported by National Energy SO Open Data. Registers from 29 January 2021 to 11 August 2026 are copies NESO released to QueueQuant on 19 October 2026 under the Environmental Information Regulations 2004 (request FOI/26/226). Later registers are QueueWatch’s own downloads from NESO’s Data Portal. Contains data from DESNZ’s Renewable Energy Planning Database. Contains public sector information licensed under the Open Government Licence v3.0.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO