Thorpe Marsh Green Energy Centre
- Connection date
- 30 Oct 2030
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Demand + Storage + Solar + Onshore wind
- Total capacity
- 1,025 MW
- Connected now
- 0 MW
- Still to connect
- 1,025 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001724
- In the register since
- January 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 400 | 400 | 30 Oct 2030 | Not stated | Awaiting Consents |
| 2 | 0 | 625 | 1,025 | 31 Aug 2032 | Not stated | Awaiting Consents |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Aug 2025 registerCustomer changed from INNOVA RENEWABLES LIMITED to THORPE MARSH NG LTD
- 27 Jun 2025 registerStage 1: Technology changed from Storage, Solar to Demand, Storage, Solar, Onshore wind
- 27 Jun 2025 registerStage 2: Technology changed from Storage, Solar to Demand, Storage, Solar, Onshore wind
- 29 Apr 2025 registerCustomer changed from THORPE MARSH NG LTD to INNOVA RENEWABLES LIMITED
- 28 Mar 2025 registerCustomer changed from INNOVA RENEWABLES LIMITED to THORPE MARSH NG LTD
- 28 Nov 2023 registerConnection point changed from Thorpe Marsh A 400kV Substation to Thorpe Marsh 400kV Substation
- 31 Oct 2023 registerStage 1: Connection date moved from 31 Oct 2030 to 30 Oct 2030 (1 day earlier)
- 28 Jul 2023 registerNew stage added (625 MW from 31 Aug 2032)
- 23 Dec 2022 registerSubstation name updated in the register (from Thorpe Marsh A 400kV to Thorpe Marsh A 400kV Substation)
- 28 Jan 2022 registerAdded to the register
Also at Thorpe Marsh 400kV Substation
Substation view3 other projects, 2.7 GW still to connect at this substation in total. 1.5 GW is due to connect here before this project’s connection date of 30 Oct 2030.
- Thorpe Marsh Energy ParkTHORPE MARSH GREEN ENERGY HUB LIMITED, Storage, Gate 2Jan 20271.4 GW
- Thorpe Marsh 1 (Tertiary)ENSO GREEN HOLDINGS I LIMITED, Storage with solar or wind, Not statedOct 202857 MW
- Fenwick Solar ProjectFENWICK SOLAR PROJECT LIMITED, Storage with solar or wind, Not statedApr 2032238 MW