Projects / England and Wales
- Connection date
- 6 Dec 2036
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar + Offshore wind
- Total capacity
- 2,500 MW
- Connected now
- 0 MW
- Still to connect
- 2,500 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002046
- Tracked since
- 14 Aug 2026
Change history
Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.
No changes since 14 Aug 2026. Follow this project to see the next one on your watchlist.
Also queued at Chickerell 400kV Substation
Substation view4 other projects, 3.5 GW still to connect at this substation in total.
- Chickerell Solar PV & BESSCHICKERELL STORAGE LIMITED, Storage, Gate 2Oct 2028400 MW
- BESS North FarmREWE 5 LIMITED, Storage, Gate 1Nov 2031150 MW
- ChickerellENSO GREEN HOLDINGS X LIMITED, Storage with solar or wind, Gate 1Dec 2036400 MW
- ChickerellSSE GENERATION LIMITED, Thermal (gas, biomass, waste), Not statedConnected47 MW