Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / North Scotland

Caledonia Offshore Wind Farm

CALEDONIA OFFSHORE WIND FARM LIMITED at Greens 400kV Substation

Connection date
31 Mar 2031
Gate
Not stated
Status
Scoping
Technology
Offshore wind
Total capacity
2,000 MW
Connected now
0 MW
Still to connect
2,000 MW
Transmission owner
SSEN Transmission (SHET)
Agreement type
Direct Connection
Region
North Scotland
Project number
PRO-001436
In the register since
June 2021

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
1060060031 Mar 2031Not statedScoping
201,4002,00031 Oct 2032Not statedScoping

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 21 Jul 2026 register
    Renamed from North East Offshore Wind Farm
  • 30 Jan 2026 register
    Connection point changed from New Deer 2 400kV Substation to Greens 400kV Substation
  • 29 Aug 2025 register
    Restructured from 1 stage (2,000 MW from 31 Oct 2033) to 2 stages (600 MW from 31 Mar 2031, 1,400 MW from 31 Oct 2032). First connection date −31 months
  • 30 Jun 2023 register
    Customer changed from MORAY OFFSHORE RENEWABLE POWER LIMITED to CALEDONIA OFFSHORE WIND FARM LIMITED
  • 28 Sep 2021 register
    Connection point changed from North East 275/66kV Offshore Substation to New Deer 2 400kV Substation
  • 29 Jun 2021 register
    Added to the register

Also at Greens 400kV Substation

Substation view

1 other project, 3.5 GW still to connect at this substation in total.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.