Havbredey
- Connection date
- 30 Oct 2033
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Offshore wind
- Total capacity
- 1,500 MW
- Connected now
- 0 MW
- Still to connect
- 1,500 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-001628
- In the register since
- October 2021
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 31 Oct 2033 to 30 Oct 2033 (1 day earlier)
- 19 Dec 2025 registerMarked as Gate 1
- 21 Nov 2025 registerCustomer changed from ANAM NA MARA LIMITED to HAVBREDEY LIMITED
- 29 Jul 2025 registerCustomer changed from HAVBREDEY LIMITED to ANAM NA MARA LIMITED
- 29 Jul 2025 registerConnection point changed from NPI A 275/66kV Offshore Substation to New Dounreay 400kV substation
- 29 Apr 2025 registerCustomer changed from Northland Power UK Limited to HAVBREDEY LIMITED
- 26 Nov 2024 registerRenamed from NPI A Offshore
- 29 Oct 2021 registerAdded to the register
Also at New Dounreay 400kV substation
Substation view1 other project, 1.7 GW still to connect at this substation in total.