QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / North Scotland

Havbredey

HAVBREDEY LIMITED at New Dounreay 400kV substation

Connection date
30 Oct 2033
Gate
Gate 1
Status
Scoping
Technology
Offshore wind
Total capacity
1,500 MW
Connected now
0 MW
Still to connect
1,500 MW
Transmission owner
SSEN Transmission (SHET)
Agreement type
Direct Connection
Region
North Scotland
Project number
PRO-001628
In the register since
October 2021

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 10 Oct 2026 register
    Connection date moved from 31 Oct 2033 to 30 Oct 2033 (1 day earlier)
  • 19 Dec 2025 register
    Marked as Gate 1
  • 21 Nov 2025 register
    Customer changed from ANAM NA MARA LIMITED to HAVBREDEY LIMITED
  • 29 Jul 2025 register
    Customer changed from HAVBREDEY LIMITED to ANAM NA MARA LIMITED
  • 29 Jul 2025 register
    Connection point changed from NPI A 275/66kV Offshore Substation to New Dounreay 400kV substation
  • 29 Apr 2025 register
    Customer changed from Northland Power UK Limited to HAVBREDEY LIMITED
  • 26 Nov 2024 register
    Renamed from NPI A Offshore
  • 29 Oct 2021 register
    Added to the register

Also at New Dounreay 400kV substation

Substation view

1 other project, 1.7 GW still to connect at this substation in total.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO