Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales
Connection date
1 Mar 2030 +35 months since 9 Dec
Gate
Not stated
Status
Scoping
Planning consent
Granted 20 Sep 2023
Awel y Môr Offshore Wind Farm (EN010112) · Source: Planning Inspectorate
Technology
Offshore wind
Total capacity
1,100 MW
Connected now
0 MW
Still to connect
1,100 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-000529
In the register since
January 2021 or earlier

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 11 Aug 2026 register
    Restructured from 2 stages (574 MW from 1 Apr 2027, 526 MW from 1 Apr 2028) to 1 stage (1,100 MW from 1 Mar 2030). First connection date +35 months
  • 28 Mar 2025 register
    Renamed from Awel Y Mor Extension
  • 30 Sep 2022 register
    Restructured from 1 stage (1,100 MW from 1 Apr 2027) to 2 stages (574 MW from 1 Apr 2027, 526 MW from 1 Apr 2028)
  • 29 Apr 2022 register
    Connection point changed from Gwynt y Mor 132/33kV Offshore Substation to Bodelwyddan 400kV Substation
  • 29 Apr 2022 register
    Transmission owner changed from OFTO to NGET
  • 31 Dec 2021 register
    Capacity changed from 580 MW to 1,100 MW
  • 26 Feb 2021 register
    Connection date moved from 4 Jan 2027 to 1 Apr 2027 (+3 months)

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO

Planning consent

The planning decision for this project, from the Planning Inspectorate. NESO’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.