Halfway Energy Park
DALRIADA RENEWABLES LIMITED at New East Coast 400kV Substation
- Connection date
- 31 Oct 2035
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 1,000 MW
- Connected now
- 0 MW
- Still to connect
- 1,000 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-004062
- In the register since
- April 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerConnection point changed from Coupar Angus GSP 400kV to New East Coast 400kV Substation
- 26 Apr 2024 registerAdded to the register
Also at New East Coast 400kV Substation
Substation viewNo other projects in the register at this connection point.