East Anglia Three
EAST ANGLIA THREE LIMITED at East Anglia Project Three Offshore Platform
- Connection date
- 31 Jan 2026
- Gate
- Not stated
- Status
- Consents Approved
- Planning consent
- Granted 7 Aug 2017
The Planning Inspectorate - National Infrastructure, reference EN010056 · Source: REPD - Contract for Difference
- Allocation Round 6
- Technology
- Offshore wind
- Total capacity
- 1,320 MW
- Connected now
- 0 MW
- Still to connect
- 1,320 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000270
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Oct 2026 registerRestructured from 2 stages (1,200 MW from 31 Jan 2026, 120 MW from 31 Dec 2028) to 1 stage (1,320 MW from 31 Jan 2026)
- 22 Oct 2026 registerStage 2: Capacity changed from 100 MW to 120 MW
- 30 Apr 2021 registerConnection point changed from EA3A and EA3B 320/66kV Offshore Platform to East Anglia Project Three Offshore Platform
- 30 Apr 2021 registerStage 1: Capacity changed from 600 MW to 1,200 MW
- 30 Apr 2021 registerStage 1: Connection date moved from 1 Apr 2023 to 31 Jan 2026 (+34 months)
- 30 Apr 2021 registerStage 2: Capacity changed from 600 MW to 100 MW
- 30 Apr 2021 registerStage 2: Connection date moved from 1 Apr 2023 to 31 Dec 2028 (+69 months)
- 30 Mar 2021 registerRenamed from East Anglia 3
- 26 Feb 2021 registerStage 1: Connection date moved from 4 Jan 2023 to 1 Apr 2023 (+3 months)
- 26 Feb 2021 registerStage 2: Connection date moved from 4 Jan 2023 to 1 Apr 2023 (+3 months)
Also at East Anglia Project Three Offshore Platform
Substation viewNo other projects in the register at this connection point.