Legacy Green Energy Centre
- Connection date
- 30 Oct 2027
- Gate
- Gate 1
- Status
- Awaiting Consents
- Technology
- Storage
- Total capacity
- 1,200 MW
- Connected now
- 0 MW
- Still to connect
- 1,200 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001662
- In the register since
- October 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 400 | 400 | 30 Oct 2027 | Gate 1 | Awaiting Consents |
| 2 | 0 | 800 | 1,200 | 28 Oct 2037 | Gate 1 | Awaiting Consents |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 1 Oct 2026 registerStage 2: Marked as Gate 1
- 16 Jun 2026 registerStage 1: Marked as Gate 1
- 30 Sep 2025 registerStage removed (0 MW from 30 Oct 2032)
- 29 Jul 2025 registerStage 1: Connection date moved from 30 Oct 2026 to 30 Oct 2027 (+12 months)
- 29 Jul 2025 registerStage 2: Capacity changed from 400 MW to 0 MW
- 29 Jul 2025 registerStage 3: Capacity changed from 225 MW to 800 MW
- 29 Jul 2025 registerStage 3: Connection date moved from 28 Oct 2033 to 28 Oct 2037 (+48 months)
- 29 Apr 2025 registerStage 1: Technology changed from Storage, Solar to Storage
- 29 Apr 2025 registerStage 2: Technology changed from Storage, Solar to Storage
- 29 Apr 2025 registerStage 3: Technology changed from Storage, Solar to Storage
- 28 Jul 2023 registerRestructured from 1 stage (400 MW from 30 Oct 2026) to 3 stages (400 MW from 30 Oct 2026, 400 MW from 30 Oct 2032, 225 MW from 28 Oct 2033)
- 23 Dec 2022 registerSubstation name updated in the register (from Legacy to Legacy GSP)
- 29 Oct 2021 registerAdded to the register
Also at Legacy 400kV Substation
Substation view3 other projects, 1.7 GW still to connect at this substation in total. 57 MW is due to connect here before this project’s connection date of 30 Oct 2027.