Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales

Legacy Green Energy Centre

LEGACY GREEN ENERGY LIMITED at Legacy 400kV Substation

Connection date
30 Oct 2027
Gate
Gate 1
Status
Awaiting Consents
Technology
Storage
Total capacity
1,200 MW
Connected now
0 MW
Still to connect
1,200 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-001662
In the register since
October 2021

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
1040040030 Oct 2027Gate 1Awaiting Consents
208001,20028 Oct 2037Gate 1Awaiting Consents

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 1 Oct 2026 register
    Stage 2: Marked as Gate 1
  • 16 Jun 2026 register
    Stage 1: Marked as Gate 1
  • 30 Sep 2025 register
    Stage removed (0 MW from 30 Oct 2032)
  • 29 Jul 2025 register
    Stage 1: Connection date moved from 30 Oct 2026 to 30 Oct 2027 (+12 months)
  • 29 Jul 2025 register
    Stage 2: Capacity changed from 400 MW to 0 MW
  • 29 Jul 2025 register
    Stage 3: Capacity changed from 225 MW to 800 MW
  • 29 Jul 2025 register
    Stage 3: Connection date moved from 28 Oct 2033 to 28 Oct 2037 (+48 months)
  • 29 Apr 2025 register
    Stage 1: Technology changed from Storage, Solar to Storage
  • 29 Apr 2025 register
    Stage 2: Technology changed from Storage, Solar to Storage
  • 29 Apr 2025 register
    Stage 3: Technology changed from Storage, Solar to Storage
  • 28 Jul 2023 register
    Restructured from 1 stage (400 MW from 30 Oct 2026) to 3 stages (400 MW from 30 Oct 2026, 400 MW from 30 Oct 2032, 225 MW from 28 Oct 2033)
  • 23 Dec 2022 register
    Substation name updated in the register (from Legacy to Legacy GSP)
  • 29 Oct 2021 register
    Added to the register

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO