Bute Hydrogen Project 1
HALDANE ENERGY PROJECT 1 LIMITED at Trent Valley South Connection Node D 400kV Substation
- Connection date
- 30 Oct 2035
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Gas (CCGT)
- Total capacity
- 4,800 MW
- Connected now
- 0 MW
- Still to connect
- 4,800 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004124
- In the register since
- February 2024
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 31 Oct 2035 to 30 Oct 2035 (1 day earlier)
- 1 May 2026 registerMarked as Gate 1
- 20 Mar 2026 registerConnection point changed from Keadby GSP to Trent Valley South Connection Node D 400kV Substation
- 21 Nov 2025 registerCustomer changed from Bute Hydrogen Project 1 Limited to HALDANE ENERGY PROJECT 1 LIMITED
- 31 Jan 2025 registerTechnology changed from Gas (CCGT), Demand, Storage to Gas (CCGT)
- 27 Feb 2024 registerAdded to the register
Also at Trent Valley South Connection Node D 400kV Substation
Substation view3 other projects, 6.4 GW still to connect at this substation in total. 1.2 GW is due to connect here before this project’s connection date of 30 Oct 2035.