Mablethorpe Green Energy Centre
- Connection date
- 30 Oct 2033
- Gate
- Gate 1
- Status
- Awaiting Consents
- Technology
- Demand + Storage + Solar
- Total capacity
- 1,025 MW
- Connected now
- 0 MW
- Still to connect
- 1,025 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002255
- In the register since
- April 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Jan 2026 registerCustomer changed from MABLETHORPE GREEN ENERGY CENTRE LIMITED to MABLETHORPE NG LIMITED
- 19 Dec 2025 registerMarked as Gate 1
- 30 Sep 2025 registerStage removed (0 MW from 30 Oct 2039)
- 27 Jun 2025 registerRestructured from 1 stage (1,025 MW from 30 Oct 2033) to 2 stages (1,025 MW from 30 Oct 2033, 0 MW from 30 Oct 2039)
- 29 Apr 2025 registerCustomer changed from MABLETHORPE NG LIMITED to MABLETHORPE GREEN ENERGY CENTRE LIMITED
- 28 Mar 2025 registerCustomer changed from MABLETHORPE GREEN ENERGY CENTRE LIMITED to MABLETHORPE NG LIMITED
- 28 Apr 2023 registerAdded to the register
Also at Mablethorpe 400kV Substation
Substation view1 other project, 1.3 GW still to connect at this substation in total.