Dogger Bank South East
RWE Renewables UK Dogger Bank South (East) Limited at Birkhill Wood 400kV Substation
- Connection date
- 30 Oct 2030
- Gate
- Not stated
- Status
- Scoping
- Technology
- Offshore wind
- Total capacity
- 1,450 MW
- Connected now
- 0 MW
- Still to connect
- 1,450 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001375
- Tracked since
- 14 Aug 2026
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 400 | 400 | 30 Oct 2030 | Not stated | Scoping |
| 2 | 0 | 1,050 | 1,450 | 30 Nov 2031 | Not stated | Scoping |
Change history
Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.
No changes since 14 Aug 2026. Follow this project to see the next one on your watchlist.
Also queued at Birkhill Wood 400kV Substation
Substation view2 other projects, 4.4 GW still to connect at this substation in total.