QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales
Connection date
1 Apr 2025
Gate
Not stated
Status
Consents Approved
Technology
Offshore wind
Total capacity
1,200 MW
Connected now
0 MW
Still to connect
1,200 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-000409
In the register since
January 2021 or earlier

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 19 Dec 2025 register
    Connection point changed from Teeside Connection Node A 132kV Substation to Lackenby 400kV Substation
  • 30 Sep 2025 register
    Connection point changed from Lackenby GSP to Teeside Connection Node A 132kV Substation
  • 23 Dec 2022 register
    Substation name updated in the register (from Lackenby to Lackenby GSP)
  • 29 Jul 2022 register
    Customer changed from DOGGERBANK OFFSHORE WIND FARM PROJECT 3 HOLDCO LIMITED to DOGGERBANK OFFSHORE WIND FARM PROJECT 3 PROJCO LIMITED
  • 29 Apr 2022 register
    Capacity changed from 1,320 MW to 1,200 MW
  • 30 Mar 2022 register
    Connection date moved from 1 Apr 2024 to 1 Apr 2025 (+12 months)
  • 28 Jan 2022 register
    Renamed from Dogger Bank Project 2
  • 30 Nov 2021 register
    Capacity changed from 1,500 MW to 1,320 MW
  • 28 May 2021 register
    Connection point changed from Dogger Bank 220kV Offshores to Lackenby
  • 26 Feb 2021 register
    Connection date moved from 4 Jan 2024 to 1 Apr 2024 (+3 months)

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO