Every change to the register

299 changes across 12 registers since 14 Aug 2026, newest first.

Each count is a number of changes, not projects. All changes (299) also includes 9 changes that fit no other category: 8 substation renamings and 1 removed gate marking. No change is in more than one category.

Register of 1 Oct 2026

32 changes compared with 28 Sep 2026

  • Strathy Wood Wind FarmNorth Scotland, Onshore windStage 1: Connection date moved from 30 Sep 2026 to 31 Dec 2029 (+39 months)+39 mo
  • Strathy Wood Wind FarmNorth Scotland, Onshore windStage 2: Connection date moved from 30 Sep 2026 to 31 Dec 2029 (+39 months)+39 mo
  • Fleet (Tertiary)England and Wales, SolarConnection date moved from 31 Oct 2026 to 30 Jul 2029 (+33 months)+33 mo
  • Middleton BESSEngland and Wales, StorageConnection date moved from 30 Nov 2026 to 31 May 2029 (+30 months)+30 mo
  • Cellarhead 400kV Energy StorageEngland and Wales, StorageConnection date moved from 16 Jul 2027 to 13 Sep 2028 (+14 months)+14 mo
  • WarleyEngland and Wales, StorageConnection date moved from 31 Aug 2027 to 30 Oct 2028 (+14 months)+14 mo
  • Cilfynydd Green Energy CentreEngland and Wales, Storage with solar or windStage 1: Connection date moved from 30 Oct 2028 to 30 Oct 2029 (+12 months)+12 mo
  • West WeybridgeEngland and Wales, StorageConnection date moved from 31 Oct 2027 to 30 Sep 2028 (+11 months)+11 mo
  • Smeaton BESSSouth Scotland, StorageConnection date moved from 30 Sep 2027 to 31 Jul 2028 (+10 months)+10 mo
  • Gastard BESSEngland and Wales, StorageLeft the register (200 MW from 15 Nov 2037)200 MW
  • Lambeeth 240MWEngland and Wales, StorageLeft the register (240 MW from 31 Dec 2037)240 MW
  • Middleton BESSEngland and Wales, StorageGiven a Gate 2 connection offerGate 2
  • Smeaton BESSSouth Scotland, StorageGiven a Gate 2 connection offerGate 2
  • Strathy Wood Wind FarmNorth Scotland, Onshore windStage 1: Given a Gate 2 connection offerGate 2
  • Strathy Wood Wind FarmNorth Scotland, Onshore windStage 2: Given a Gate 2 connection offerGate 2
  • West WeybridgeEngland and Wales, StorageGiven a Gate 2 connection offerGate 2
  • Brunt Hill Wind FarmSouth Scotland, Storage with solar or windTransmission owner changed from SHET to SPT
  • Cloiche Wind FarmNorth Scotland, Onshore windConnection point changed from Cloich 132kV Substation to Cloiche 132/33kV Substation
  • Cloiche Wind FarmNorth Scotland, Onshore windTransmission owner changed from SPT to SHET
  • Galileo 14 LtdEngland and Wales, StorageMarked as Gate 1
  • HalbeathSouth Scotland, Storage with solar or windMarked as Gate 1
  • KirkbyEngland and Wales, StorageConnection point changed from Kirkby 275kV Substation to Kirkby 275/33kV Substation
  • KirkbyEngland and Wales, StorageConnection point changed from Kirkby 275kV Substation to Kirkby 275/33kV Substation
  • Legacy Green Energy CentreEngland and Wales, StorageStage 2: Marked as Gate 1
  • Lochay (Part of Killin Cascade Hydro Scheme)North Scotland, Hydro & marineConnection point changed from Lochay GSP to Lochay 132/11kV Substation
  • Lochay (Part of Killin Cascade Hydro Scheme)North Scotland, Hydro & marineConnection point changed from Lochay GSP to Lochay 132/11kV Substation
  • Middleton BESSEngland and Wales, StorageStatus changed from Scoping to Under Construction/Commissioning
  • Nether Pitforthie BESSNorth Scotland, StorageConnection point changed from Fiddes GSP to FIDDES 275/33KV GRID SUPPLY POINT SUBSTATION
  • Nether Pitforthie BESSNorth Scotland, StorageMarked as Gate 1
  • North Lowther Energy InitiativeSouth Scotland, Onshore windCustomer changed from NLEI LTD to Glensalloch Wind Farm Limited
  • RugeleyEngland and Wales, StorageTechnology changed from Coal to Storage
  • Smeaton BESSSouth Scotland, StorageStatus changed from Scoping to Consents Approved

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO