Every change to the register
299 changes across 12 registers since 14 Aug 2026, newest first.
Each count is a number of changes, not projects. All changes (299) also includes 9 changes that fit no other category: 8 substation renamings and 1 removed gate marking. No change is in more than one category.
Register of 1 Oct 2026
32 changes compared with 28 Sep 2026
- Strathy Wood Wind FarmNorth Scotland, Onshore windStage 1: Connection date moved from 30 Sep 2026 to 31 Dec 2029 (+39 months)+39 mo
- Strathy Wood Wind FarmNorth Scotland, Onshore windStage 2: Connection date moved from 30 Sep 2026 to 31 Dec 2029 (+39 months)+39 mo
- Fleet (Tertiary)England and Wales, SolarConnection date moved from 31 Oct 2026 to 30 Jul 2029 (+33 months)+33 mo
- Middleton BESSEngland and Wales, StorageConnection date moved from 30 Nov 2026 to 31 May 2029 (+30 months)+30 mo
- Cellarhead 400kV Energy StorageEngland and Wales, StorageConnection date moved from 16 Jul 2027 to 13 Sep 2028 (+14 months)+14 mo
- WarleyEngland and Wales, StorageConnection date moved from 31 Aug 2027 to 30 Oct 2028 (+14 months)+14 mo
- Cilfynydd Green Energy CentreEngland and Wales, Storage with solar or windStage 1: Connection date moved from 30 Oct 2028 to 30 Oct 2029 (+12 months)+12 mo
- West WeybridgeEngland and Wales, StorageConnection date moved from 31 Oct 2027 to 30 Sep 2028 (+11 months)+11 mo
- Smeaton BESSSouth Scotland, StorageConnection date moved from 30 Sep 2027 to 31 Jul 2028 (+10 months)+10 mo
- Gastard BESSEngland and Wales, StorageLeft the register (200 MW from 15 Nov 2037)200 MW
- Lambeeth 240MWEngland and Wales, StorageLeft the register (240 MW from 31 Dec 2037)240 MW
- Middleton BESSEngland and Wales, StorageGiven a Gate 2 connection offerGate 2
- Smeaton BESSSouth Scotland, StorageGiven a Gate 2 connection offerGate 2
- Strathy Wood Wind FarmNorth Scotland, Onshore windStage 1: Given a Gate 2 connection offerGate 2
- Strathy Wood Wind FarmNorth Scotland, Onshore windStage 2: Given a Gate 2 connection offerGate 2
- West WeybridgeEngland and Wales, StorageGiven a Gate 2 connection offerGate 2
- Brunt Hill Wind FarmSouth Scotland, Storage with solar or windTransmission owner changed from SHET to SPT
- Cloiche Wind FarmNorth Scotland, Onshore windConnection point changed from Cloich 132kV Substation to Cloiche 132/33kV Substation
- Cloiche Wind FarmNorth Scotland, Onshore windTransmission owner changed from SPT to SHET
- Galileo 14 LtdEngland and Wales, StorageMarked as Gate 1
- HalbeathSouth Scotland, Storage with solar or windMarked as Gate 1
- KirkbyEngland and Wales, StorageConnection point changed from Kirkby 275kV Substation to Kirkby 275/33kV Substation
- KirkbyEngland and Wales, StorageConnection point changed from Kirkby 275kV Substation to Kirkby 275/33kV Substation
- Legacy Green Energy CentreEngland and Wales, StorageStage 2: Marked as Gate 1
- Lochay (Part of Killin Cascade Hydro Scheme)North Scotland, Hydro & marineConnection point changed from Lochay GSP to Lochay 132/11kV Substation
- Lochay (Part of Killin Cascade Hydro Scheme)North Scotland, Hydro & marineConnection point changed from Lochay GSP to Lochay 132/11kV Substation
- Middleton BESSEngland and Wales, StorageStatus changed from Scoping to Under Construction/Commissioning
- Nether Pitforthie BESSNorth Scotland, StorageConnection point changed from Fiddes GSP to FIDDES 275/33KV GRID SUPPLY POINT SUBSTATION
- Nether Pitforthie BESSNorth Scotland, StorageMarked as Gate 1
- North Lowther Energy InitiativeSouth Scotland, Onshore windCustomer changed from NLEI LTD to Glensalloch Wind Farm Limited
- RugeleyEngland and Wales, StorageTechnology changed from Coal to Storage
- Smeaton BESSSouth Scotland, StorageStatus changed from Scoping to Consents Approved