Machair Offshore Wind Farm
Scottish Power Renewables (UK) Limited at Machair 275/66kV Offshore Substation
- Connection date
- 16 Sep 2033
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Application submitted 25 Jun 2026
Marine Scotland · Source: REPD - Technology
- Offshore wind
- Total capacity
- 2,000 MW
- Connected now
- 0 MW
- Still to connect
- 2,000 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-001392
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Oct 2024 registerRenamed from OWF1 Offshore
- 29 Oct 2024 registerConnection point changed from OWF1 275/66kV Offshore Substation to Machair 275/66kV Offshore Substation
- 29 Oct 2024 registerConnection date moved from 30 Apr 2028 to 16 Sep 2033 (+65 months)
- 26 Feb 2021 registerConnection point changed from Hunterston 400kV Substation to OWF1 275/66kV Offshore Substation
Also at Machair 275/66kV Offshore Substation
Substation viewNo other projects in the register at this connection point.