Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales

Berwick Bank Offshore Wind Farm C

BERWICK BANK C LIMITED at Blyth 400kV Substation

Connection date
30 Nov 2029
Gate
Not stated
Status
Scoping
Technology
Offshore wind
Total capacity
1,800 MW
Connected now
0 MW
Still to connect
1,800 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-000513
In the register since
January 2021 or earlier

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 28 Nov 2023 register
    Connection date moved from 31 Oct 2031 to 30 Nov 2029 (−23 months)
  • 23 Dec 2022 register
    Connection point changed from Seagreen Platform 3A & 3B to Blyth 400kV Substation
  • 29 Apr 2022 register
    Renamed from Seagreen Phase 3
  • 29 Apr 2022 register
    Capacity changed from 1,850 MW to 1,800 MW
  • 29 Apr 2022 register
    Connection date moved from 14 Nov 2036 to 31 Oct 2031 (−60 months)
  • 30 Mar 2022 register
    Customer changed from MARR BANK WIND LIMITED to BERWICK BANK C LIMITED
  • 30 Nov 2021 register
    Transmission owner changed from SPT to NGET

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO