NatPower Kinoulton Green Energy Park
DALBY ENERGY LIMITED at West Anglia Connection Node C 400kV Substation
- Connection date
- 31 Oct 2034 −2 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 1,330 MW
- Connected now
- 0 MW
- Still to connect
- 1,330 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004333
- In the register since
- December 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 31 Dec 2034 to 31 Oct 2034 (−2 months)
- 10 Apr 2026 registerMarked as Gate 1
- 29 Aug 2025 registerCustomer changed from NP SPV32 LIMITED to DALBY ENERGY LIMITED
- 29 Jul 2025 registerConnection point changed from Grendon 400kV Substation to West Anglia Connection Node C 400kV Substation
- 24 Dec 2024 registerAdded to the register
Also at West Anglia Connection Node C 400kV Substation
Substation view2 other projects, 2.1 GW still to connect at this substation in total.