Stromar Offshore Windfarm
Stromar Offshore Wind Farm Limited at Greens 400kV Substation
- Connection date
- 31 Oct 2033
- Gate
- Not stated
- Status
- Scoping
- Technology
- Offshore wind
- Total capacity
- 1,500 MW
- Connected now
- 0 MW
- Still to connect
- 1,500 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-001530
- In the register since
- June 2021
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 1,000 | 1,000 | 31 Oct 2033 | Not stated | Scoping |
| 2 | 0 | 500 | 1,500 | 31 Dec 2035 | Not stated | Scoping |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Jan 2026 registerConnection point changed from New Deer 2 400kV Substation to Greens 400kV Substation
- 27 Jun 2025 registerConnection point changed from Cygnus 220/66kV Offshore Substation to New Deer 2 400kV Substation
- 30 May 2025 registerNew stage added (500 MW from 31 Dec 2035)
- 29 Apr 2025 registerRenamed from Cygnus Offshore Windfarm
- 29 Apr 2025 registerCustomer changed from Renantis UK Limited to Stromar Offshore Wind Farm Limited
- 28 Mar 2025 registerCustomer changed from Nadara Limited to Renantis UK Limited
- 28 Feb 2025 registerCustomer changed from RENANTIS UK LIMITED to Nadara Limited
- 30 Jul 2024 registerCustomer changed from ORSTED (UK) LIMITED to RENANTIS UK LIMITED
- 28 Jun 2024 registerCustomer changed from RENANTIS UK LIMITED to ORSTED (UK) LIMITED
- 31 Jan 2023 registerCustomer changed from FALCK RENEWABLES WIND LIMITED to RENANTIS UK LIMITED
- 29 Jun 2021 registerAdded to the register
Also at Greens 400kV Substation
Substation view1 other project, 3.5 GW still to connect at this substation in total. 2 GW is due to connect here before this project’s connection date of 31 Oct 2033.