Vicarage Drove BESS
UK Transition Power Holdings Limited at Trent Valley South Connection Node A 400kV
- Connection date
- 30 Oct 2034
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 1,200 MW
- Connected now
- 0 MW
- Still to connect
- 1,200 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004943
- In the register since
- June 2025
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 1 May 2026 registerMarked as Gate 1
- 14 Apr 2026 registerConnection point changed from Trent Valley South Connection Node A 400k to Trent Valley South Connection Node A 400kV
- 12 Dec 2025 register1,200 MW no longer connected
- 27 Jun 2025 registerAdded to the register
Also at Trent Valley South Connection Node A 400kV
Substation view2 other projects, 2.5 GW still to connect at this substation in total.