Little Horsted Energy Park
ELEMENTS GREEN DEVELOPMENT LTD at Sussex and Romney Connection Node A 400kV Substation
- Connection date
- 31 Oct 2037
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 1,260 MW
- Connected now
- 0 MW
- Still to connect
- 1,260 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003624
- Tracked since
- 14 Aug 2026
Change history
Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.
No changes since 14 Aug 2026. Follow this project to see the next one on your watchlist.
Also queued at Sussex and Romney Connection Node A 400kV Substation
Substation view10 other projects, 4 GW still to connect at this substation in total.
- NinfieldNinfield 10 Renewables Limited, Storage with solar or wind, Gate 1Oct 20301 GW
- Little HorstedLightsource Renewable UK Development Limited, Storage with solar or wind, Gate 1Oct 203757 MW
- KXP Alpha 1 Little HorstedKXP ALPHA I LIMITED, Storage, Gate 1Oct 203799.9 MW
- KXP Alpha 2 Little HorstedKXP ALPHA II LIMITED, Storage, Not statedOct 203799.9 MW
- KXP Alpha 3 Little HorstedKXP ALPHA III LIMITED, Storage, Gate 1Oct 203799.9 MW
- New Little Horsted 200MW Solar and BESSPRIVATE ENERGY PARTNERS (UK) LTD, Storage with solar or wind, Gate 1Oct 2037200 MW
- Ninfield BESSKona Energy Limited, Storage, Gate 1Oct 2037225 MW
- STABLE GREEN ENERGYLH NGET GRID SERVICES LIMITED, Storage, Not statedOct 2037500 MW