Ferrybridge D
- Connection date
- 4 Oct 2030
- Gate
- Not stated
- Status
- Scoping
- Technology
- Gas (CCGT) + Demand + Storage + Hydrogen + Gas (OCGT)
- Total capacity
- 1,420 MW
- Connected now
- 0 MW
- Still to connect
- 1,420 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001020
- In the register since
- January 2021 or earlier
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 1,220 | 1,220 | 4 Oct 2030 | Not stated | Scoping |
| 2 | 0 | 200 | 1,420 | 1 Jun 2034 | Not stated | Awaiting Consents |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Sep 2025 registerStage 1: Capacity changed from 310 MW to 1,220 MW
- 30 Sep 2025 registerStage 2: Capacity changed from 910 MW to 200 MW
- 30 Sep 2025 registerStage 2: Connection date moved from 4 Oct 2030 to 1 Jun 2034 (+44 months)
- 30 Sep 2025 registerStage removed (200 MW from 1 Jun 2034)
- 29 Jul 2025 registerStage 1: Connection date moved from 6 Oct 2028 to 4 Oct 2030 (+24 months)
- 29 Jul 2025 registerStage 1: Technology changed from Gas (CCGT), Demand, Storage, Gas (OCGT) to Gas (CCGT), Demand, Storage, Gas (OCGT), Hydrogen
- 29 Jul 2025 registerStage 2: Technology changed from Gas (CCGT), Demand, Storage, Gas (OCGT) to Gas (CCGT), Demand, Storage, Gas (OCGT), Hydrogen
- 29 Jul 2025 registerRestructured from 1 stage (600 MW from 1 Jun 2034) to 1 stage (200 MW from 1 Jun 2034)
- 29 Apr 2025 registerStage 1: Technology changed from Gas (CCGT), Storage, Gas (OCGT) to Gas (CCGT), Demand, Storage, Gas (OCGT)
- 29 Apr 2025 registerStage 2: Technology changed from Gas (CCGT), Storage, Gas (OCGT) to Gas (CCGT), Demand, Storage, Gas (OCGT)
- 29 Apr 2025 registerStage 3: Technology changed from Gas (CCGT), Storage, Gas (OCGT) to Gas (CCGT), Demand, Storage, Gas (OCGT)
- 29 Aug 2023 registerStage 1: Technology changed from Gas (CCGT) to Gas (CCGT), Storage, Gas (OCGT)
- 29 Aug 2023 registerStage 2: Technology changed from Gas (CCGT) to Gas (CCGT), Storage, Gas (OCGT)
- 29 Aug 2023 registerStage 3: Technology changed from Gas (CCGT) to Gas (CCGT), Storage, Gas (OCGT)
- 28 Apr 2023 registerRestructured from 1 stage (1,820 MW from 1 Sep 2026) to 3 stages (310 MW from 6 Oct 2028, 910 MW from 4 Oct 2030, 600 MW from 1 Jun 2034). First connection date +25 months
- 28 Feb 2023 registerConnection point changed from Ferrybridge GSP to Ferrybridge C 275kV Substation
- 23 Dec 2022 registerSubstation name updated in the register (from Ferrybridge to Ferrybridge GSP)
- 26 Feb 2021 registerConnection date moved from 9 Jan 2026 to 1 Sep 2026 (+8 months)
Also at Ferrybridge C 275kV Substation
Substation view1 other project, 1.7 GW still to connect at this substation in total.