Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Grid outages and the connections due by 2030

Connecting a project to the transmission network needs outages: circuits and equipment taken out of service so that the connection works can be built and commissioned safely. This page shows the outage figures that NESO and the three onshore transmission owners publish, and the connections due by 2030 in NESO’s TEC register: how many will need outages in each transmission owner’s area, against how much of its planned outage work that owner carries out. We stop at 2030, the year NESO’s Clean Power 2030 advice works to, which is where most of NESO’s outage figures on this page come from. The transmission owners are NGET (National Grid Electricity Transmission) in England and Wales, SPT (SP Transmission) in central and southern Scotland, and SHET (SSEN Transmission) in the north of Scotland. The register figures update with each new register, and the transmission owners’ figures with their yearly reports.

Who this page helps, and how

Developers and their contractors. Your connection needs outages to build its works, and the transmission owners don’t carry out every outage they plan. Agree yours with your transmission owner early, and plan for it moving.

Investors and lenders. Outages can delay a connection in ways the register doesn’t show. Weigh near connection dates by each transmission owner’s record.

NESO, Ofgem and DESNZ. NESO hasn’t published how many outages connecting the queue will need. Until it does, this page puts the public figures in one place.

Transmission owners. Compare your record of carrying out planned outages with the other two transmission owners’.

1. How many outages are there on the transmission network?

About 8,000 a year, NESO says: circuits and equipment taken out of service so that new connections, reinforcements and maintenance can be done safely. It counted 7,894 in 2023/24, the latest year of its yearly count. From its data on when equipment was unavailable, NESO puts half of the “system access activity” in 2023/24 down to “System Construction”, 29% to maintenance and 1.6% to “User Connection”, connecting new users. NESO doesn’t forecast how many planned outages there will be, and hasn’t published how many connecting the queue will need.

about 8,000outages a year on the transmission network, NESO says
7,894outages taken in 2023/24, the latest year in NESO’s yearly count

Outages taken on the transmission network each year

As NESO counts them, from its outage database. Its yearly count stops at 2023/24.

Outages taken
Outages taken on the transmission network each year (NESO)
YearOutages taken
2018/198,220
2019/208,004
2020/218,361
2021/228,465
2022/237,854
2023/247,894
How we measured it

About 8,000 a year is from NESO’s Clean Power 2030 advice (5 November 2024, page 39). The outages taken each year are from its Clean Power 2030 data workbook (sheet NA1), drawn from its outage database. The workbook also has rows 5% to 20% above the 2023/24 figure. These are flat uplifts, not a forecast, so we leave them out. The split of 2023/24 is of “the overall system access activity”, which NESO took from unavailability data in its system performance report for 2023/24, not of outages; it is Figure 9 of NESO’s Transmission Acceleration consultation (February 2025, pages 53 and 54). That NESO doesn’t forecast outage numbers is its reply to an Environmental Information Regulations request (FOI/25/094, 10 September 2025). NESO’s own figures differ in places: its Clean Power 2030 advice says 40% of outages are agreed 12 months ahead (page 39), its Clean Power 2030 next steps (June 2025) 50% (page 25); and its web page “What happens when there’s a request for an outage?” puts the final year-ahead plan at around 2,500 outages, its February 2025 consultation the plan for 2025/26 at over 4,000 (page 55). NESO’s Grid Code proposal GC0191 (October 2026) gives 8,100 planned outages for 2025/26 (page 17).

2. How many of their planned outages do the transmission owners carry out?

Each transmission owner plans its outages a year ahead, in a plan submitted at week 49 (early December) of the year before. It then reports how many of them it carried out. In 2025/26, NGET carried out 1,032 of the 2,253 outages in its year-ahead plan (46%), SPT 563 of 984 (57%) and SHET 518 of 740 (70%). SPT’s report says the other 421 didn’t start. NGET’s and SHET’s reports don’t say what became of theirs.

1,032 of 2,253outages in NGET’s 2025/26 year-ahead plan carried out
46% to 70%of each transmission owner’s 2025/26 plan carried out
Transmission ownerNGETSPTSHET

Each transmission owner’s year-ahead plan and how much of it was carried out

Each bar is one year’s plan; the lower part is the outages carried out.

Carried outNot carried out
NGET’s year-ahead plans and the outages carried out
YearIn the year-ahead planCarried outNot carried outShare carried out
2021/221,9141,16475061%
2022/232,1551,0851,07050%
2023/241,81083897246%
2024/252,0551,0371,01850%
2025/262,2531,0321,22146%
How we measured it

Each owner reports under the GB Network Access Policy (Appendix A, KPI 1): the outages in its year-ahead plan submitted at week 49, how many of these it carried out in the regulatory year, and the share. The reports call these outages “delivered”; this page says “carried out”. Either way, they are the plan’s outages that went ahead, and all three count only those, not every outage done in the year: NGET reports its “YA outages delivered” against its plan; SHET counts “only the … planned outages (KPI 1b) included in the week 49 … baseline plan”; and SPT “delivered 563 of the 984 planned outages in the year ahead plan” in 2025/26, its KPI 9 table giving 349 on time, 128 early, 86 late and 421 that didn’t start. Outages added during the year come on top. The reports differ: NGET’s and SHET’s plans count in-service bookings too, works done without taking the equipment out of service, such as telecoms works or works that risk tripping a circuit, while SPT’s report doesn’t say whether its plan does. None says how close to plan counts as on time. Each figure is the report’s own, with its page, in the reviewed record the page is built from.

3. How many connections are due by 2030, and where?

Many projects connect in stages, parts of their capacity each with its own connection date. On 3 November 2026, NESO’s TEC register had 626 stages still to connect with connection dates from 2026 to 2030: 144.7 GW at 443 substations. 52 of the 2026 stages were already past their connection date. 2028 and 2029 have the most, with 173 and 167 stages.

As Which connection dates slip least? shows, connection dates this close are often pushed back. From 2021 to 2025, 40% of those due within the year were pushed back within it, and 26% of those due two to four years ahead.

626 stagesstill to connect, with connection dates from 2026 to 2030
443substations they connect at

The connections due each year, 2026 to 2030

Stages still to connect, by the year of their own connection date and by transmission owner. Press part of a bar to list its stages.

NGETSPTSHET
Stages still to connect by the year of their connection date, 2026 to 2030
Due inNGETSPTSHETAll stagesMW still to connectSubstations
2026, already past its connection date261795211,641.345
2026, still to come2529713.58
20275432139916,216.487
202897463017334,985.6143
202976543716745,489.5143
203043374612635,625.5119
2026 to 2030298191137626144,671.8–

What it means: The connections due by 2030 are spread over hundreds of substations, and each transmission owner carries out only part of the outages it plans a year ahead.

How we measured it

A stage is a row of the register still to connect. Its year is the year of its own connection date (the register’s MW Effective From), and it connects at its project’s connection site. “Already past its connection date” means before the latest register. Stages still to connect with connection dates before 2026 (50 stages, 5.3 GW) and those due after 2030 are left out. A substation with stages due in more than one year counts once in each of those years, and once in the total. How often connection dates were pushed back comes from Which connection dates slip least?, over the full years 2021 to 2025: how often a connection date that far ahead at the start of a year was pushed back within that year. That is history, not a forecast. The page doesn’t count outages per connection: one outage can serve the works of several connections, and others serve none.

What if your connection date is pushed back?

QueueQuant values your project across thousands of possible futures for its connection date and the market, and tells you whether to hold, cut MW, sell or walk away, and what would change that answer.

Price my projectSee use cases

How to cite this page

You’re welcome to quote our figures, charts and findings with this credit:

QueueWatch by QueueQuant, ‘Grid outages and the connections due by 2030’, queuequant.com/queuewatch/grid-outages-2030/ (data to 3 November 2026). Contains data from NESO’s TEC register. Supported by National Energy SO Open Data. Outage figures from the Network Access Policy KPI reports of National Grid Electricity Transmission, SP Transmission and SSEN Transmission, and from NESO’s publications.

Supported by National Energy SO Open Data. Registers from 29 January 2021 to 11 August 2026 are copies NESO released to QueueQuant on 19 October 2026 under the Environmental Information Regulations 2004 (request FOI/26/226). Later registers are QueueWatch’s own downloads from NESO’s Data Portal. Outage figures from the Network Access Policy KPI reports of National Grid Electricity Transmission, SP Transmission and SSEN Transmission, and from NESO’s publications.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO