Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales

Overton Green Energy Centre

OVERTON NG LIMITED at Overton 275kV

Connection date
24 Oct 2035
Gate
Not stated
Status
Awaiting Consents
Technology
Demand + Storage + Solar
Total capacity
1,025 MW
Connected now
0 MW
Still to connect
1,025 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-002252
In the register since
April 2023

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 10 Apr 2026 register
    Connection point changed from Overton 400kV Substation to Overton 275kV
  • 29 Aug 2025 register
    Customer changed from INNOVA RENEWABLES LIMITED to OVERTON NG LIMITED
  • 27 Jun 2025 register
    Technology changed from Storage, Solar to Demand, Storage, Solar
  • 29 Apr 2025 register
    Customer changed from OVERTON NG LIMITED to INNOVA RENEWABLES LIMITED
  • 28 Mar 2025 register
    Customer changed from INNOVA RENEWABLES LIMITED to OVERTON NG LIMITED
  • 28 Apr 2023 register
    Added to the register

Also at Overton 275kV

Substation view

1 other project, 2.4 GW still to connect at this substation in total. 1.4 GW is due to connect here before this project’s connection date of 24 Oct 2035.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO