Dogger Bank South West
RWE RENEWABLES UK DOGGER BANK SOUTH (WEST) LIMITED at Birkhill Wood 400kV Substation
- Connection date
- 30 Oct 2030
- Gate
- Not stated
- Status
- Scoping
- Technology
- Offshore wind
- Total capacity
- 1,450 MW
- Connected now
- 0 MW
- Still to connect
- 1,450 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001386
- In the register since
- June 2021
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 400 | 400 | 30 Oct 2030 | Not stated | Scoping |
| 2 | 0 | 1,050 | 1,450 | 30 Nov 2031 | Not stated | Scoping |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerConnection point changed from Wylfa 400kV Substation to Birkhill Wood 400kV Substation
- 27 Jun 2025 registerCustomer changed from RWE RENEWABLES UK LIMITED to RWE RENEWABLES UK DOGGER BANK SOUTH (WEST) LIMITED
- 24 Dec 2024 registerRestructured from 1 stage (1,500 MW from 1 Apr 2033) to 2 stages (400 MW from 30 Oct 2030, 1,050 MW from 30 Nov 2031). First connection date −29 months
- 26 Mar 2024 registerRenamed from North Sea B (Irish Sea)
- 23 Dec 2022 registerSubstation name updated in the register (from Wylfa 400kV to Wylfa 400kV Substation)
- 31 May 2022 registerConnection date moved from 1 Jan 2033 to 1 Apr 2033 (+3 months)
- 28 Jan 2022 registerRenamed from Irish Sea Offshore Substation
- 29 Jun 2021 registerAdded to the register
Also at Birkhill Wood 400kV Substation
Substation view2 other projects, 4.4 GW still to connect at this substation in total.