PIVOTED POWER LLP
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Seabank (Tertiary) | SEABANK 400/33kV SUBSTATION | Storage | 49.9 | 1 Nov 2023 Past date | Gate 1 | Awaiting Consents |
| Indian Queens | Indian Queens 400kV Substation | Storage | 47.5 | 30 Jul 2024 Past date | Not stated | Consents Approved |
| Mannington | Mannington 400kV Substation | Storage with solar or wind | 47.5 | 30 Nov 2025 Past date | Not stated | Consents Approved |
| Norwich | Norwich Main 400kV Substation | Storage with solar or wind | 57 | 18 Dec 2025 Past date | Not stated | Consents Approved |
| Landulph | Landulph 400kV Substation | Storage with solar or wind | 57 | 18 May 2026 Past date | Not stated | Consents Approved |
| Willington | Willington East 400kV Substation | Storage | 57 | 30 Jun 2026 Past date | Gate 1 | Scoping |
| Braintree | Braintree 400kV Substation | Storage with solar or wind | 57 | 30 May 2027 +31 mo | Gate 2 | Consents Approved |
| Oldbury (Tertiary) | Oldbury 275kV Substation | Storage | 57 | 30 Jun 2027 | Gate 1 | Awaiting Consents |
| Kirkby (Tertiary) | Kirkby 275/33kV Substation | Storage with solar or wind | 57 | 30 Aug 2027 | Gate 1 | Scoping |
| Axminster | Axminster 400kV Substation | Storage | 49.9 | 31 Oct 2027 | Gate 1 | Scoping |
| Whitson | Whitson 275kV Substation | Storage | 49.9 | 31 Oct 2027 | Gate 1 | Scoping |
| Exeter (Tertiary) | Exeter 400kV Substation | Storage with solar or wind | 57 | 16 Jun 2028 | Not stated | Awaiting Consents |
| Carrington | Carrington 275kV Substation | Storage | 57 | 31 Oct 2028 | Gate 1 | Awaiting Consents |
| Kearsley | Kearsley 275kV Substation | Storage | 49.9 | 31 Oct 2028 | Gate 1 | Awaiting Consents |
| Sellindge (Tertiary) | Sellindge 400kV Substation | Storage | 76 | 31 Oct 2028 | Not stated | Awaiting Consents |
| Spennymoor | Spennymoor 400kV Substation | Storage | 49.9 | 31 Oct 2028 | Gate 1 | Awaiting Consents |
| Burwell (Tertiary) | Burwell Main 400kV Substation | Storage | 57 | 30 Jun 2029 | Not stated | Awaiting Consents |
| Pivot Power Harker Hybrid | Harker 400/132KV Substation | Storage with solar or wind | 57 | 31 Oct 2029 | Gate 1 | Scoping |
| Bolney | Bolney 400kV Substation | Storage with solar or wind | 47.5 | 31 Jan 2031 | Not stated | Scoping |
| Alverdiscott | Alverdiscott 400kV Substation | Storage | 100 | 31 Aug 2031 +22 mo | Gate 1 | Scoping |
| Taunton | Taunton 400kV Substation | Storage | 100 | 31 Oct 2031 | Gate 1 | Awaiting Consents |
| Bredbury | Bredbury 275kV Substation | Storage | 0 | Connected | Not stated | Built |
| Bustleholme | Bustleholm GSP | Storage | 0 | Connected | Not stated | Built |
| Coventry | Coventry 275kV Substation | Storage with solar or wind | 0 | Connected | Not stated | Built |
| Cowley | Cowley 400kV Substation | Storage | 0 | Connected | Not stated | Built |
| Kemsley | Kemsley 400kV Substation | Storage | 0 | Connected | Not stated | Built |
| Sundon Pivoted Power | Sundon 400kV Substation | Solar | 0 | Connected | Not stated | Built |
Left the register since January 2021: Hutton (0 MW), Rochdale (0 MW), Tottenham (49.9 MW), West Weybridge (49.9 MW).
Recent changes
- BraintreeEngland and Wales, Storage with solar or windCapacity changed from 49.9 MW to 57 MW
- BraintreeEngland and Wales, Storage with solar or windStage removed (7.1 MW from 30 May 2027)
- BraintreeEngland and Wales, Storage with solar or windStage 1: Connection date moved from 30 Oct 2024 to 30 May 2027 (+31 months)+31 mo
- BraintreeEngland and Wales, Storage with solar or windStage 1: Status changed from Awaiting Consents to Consents Approved
- BraintreeEngland and Wales, Storage with solar or windStage 1: Given a Gate 2 connection offerGate 2
- BraintreeEngland and Wales, Storage with solar or windStage 2: Connection date moved from 30 Oct 2026 to 30 May 2027 (+7 months)+7 mo
- BraintreeEngland and Wales, Storage with solar or windStage 2: Status changed from Scoping to Consents Approved
- BraintreeEngland and Wales, Storage with solar or windStage 2: Given a Gate 2 connection offerGate 2
- KearsleyEngland and Wales, StorageMarked as Gate 1
- Pivot Power Harker HybridEngland and Wales, Storage with solar or windStatus changed from Consents Approved to Scoping
- AlverdiscottEngland and Wales, StorageStage 1: Connection date moved from 31 Oct 2029 to 31 Aug 2031 (+22 months)+22 mo
- Kirkby (Tertiary)England and Wales, Storage with solar or windMarked as Gate 1
- AxminsterEngland and Wales, StorageMarked as Gate 1
- AlverdiscottEngland and Wales, StorageStage 1: Marked as Gate 1
- AlverdiscottEngland and Wales, StorageStage 2: Marked as Gate 1
- TauntonEngland and Wales, StorageStage 1: Marked as Gate 1
- TauntonEngland and Wales, StorageStage 2: Marked as Gate 1
- Kirkby (Tertiary)England and Wales, Storage with solar or windConnection point changed from Kirkby GSP (ENW) to Kirkby 275/33kV Substation
- Pivot Power Harker HybridEngland and Wales, Storage with solar or windConnection point changed from Harker 400kV Substation to Harker 400/132KV Substation
- Pivot Power Harker HybridEngland and Wales, Storage with solar or windMarked as Gate 1
- SpennymoorEngland and Wales, StorageMarked as Gate 1
- Seabank (Tertiary)England and Wales, StorageConnection point changed from Seabank 400kV Substation to SEABANK 400/33kV SUBSTATION
- Seabank (Tertiary)England and Wales, StorageMarked as Gate 1
- CarringtonEngland and Wales, StorageMarked as Gate 1
- WillingtonEngland and Wales, StorageMarked as Gate 1
- Oldbury (Tertiary)England and Wales, StorageStage 1: Marked as Gate 1
- Oldbury (Tertiary)England and Wales, StorageStage 2: Marked as Gate 1
- WhitsonEngland and Wales, StorageMarked as Gate 1
- WhitsonEngland and Wales, StorageConnection date moved from 31 Oct 2026 to 31 Oct 2027 (+12 months)+12 mo
- BredburyEngland and Wales, Storage49.9 MW now connectedConnected
- LandulphEngland and Wales, Storage with solar or windStage 1: Connection date moved from 31 Oct 2022 to 18 May 2026 (+43 months)+43 mo
- BraintreeEngland and Wales, Storage with solar or windStage 1: Technology changed from Storage to Storage, Solar
- BraintreeEngland and Wales, Storage with solar or windStage 2: Technology changed from Storage to Storage, Solar
- BredburyEngland and Wales, StorageConnection date removed (was 14 Sep 2024)
- BredburyEngland and Wales, StorageStatus changed from Under Construction/Commissioning to Built
- KearsleyEngland and Wales, StorageConnection point changed from Kearsley 400kV Substation to Kearsley 275kV Substation
- KearsleyEngland and Wales, StorageTechnology changed from Storage to Demand, Storage
- BolneyEngland and Wales, Storage with solar or windTechnology changed from Solar to Storage, Solar
- NorwichEngland and Wales, Storage with solar or windConnection point changed from Norwich GSP to Norwich Main 400kV Substation
- Sellindge (Tertiary)England and Wales, StorageRestructured from 1 stage (49.9 MW from 1 Nov 2024) to 2 stages (49.9 MW from 31 Oct 2028, 26.1 MW from 31 Oct 2031). First connection date +48 months+48 mo
- BolneyEngland and Wales, Storage with solar or windCapacity changed from 49.9 MW to 47.5 MW
- BolneyEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2027 to 31 Jan 2031 (+39 months)+39 mo
- BolneyEngland and Wales, Storage with solar or windTechnology changed from Storage to Solar
- BredburyEngland and Wales, StorageStatus changed from Scoping to Under Construction/Commissioning
- CoventryEngland and Wales, Storage with solar or windTechnology changed from Storage to Storage, Solar
- LandulphEngland and Wales, Storage with solar or windRestructured from 1 stage (49.9 MW from 31 Oct 2022) to 2 stages (49.9 MW from 31 Oct 2022, 7.1 MW from 31 Oct 2028)
- ManningtonEngland and Wales, Storage with solar or windTechnology changed from Storage to Storage, Solar
- NorwichEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2024 to 18 Dec 2025 (+14 months)+14 mo
- Sundon Pivoted PowerEngland and Wales, SolarTechnology changed from Storage to Solar
- ManningtonEngland and Wales, Storage with solar or windStatus changed from Awaiting Consents to Consents Approved
- Exeter (Tertiary)England and Wales, Storage with solar or windStage 1: Connection date moved from 6 Dec 2036 to 16 Jun 2028 (−102 months)−102 mo
- Exeter (Tertiary)England and Wales, Storage with solar or windStage 1: Status changed from Scoping to Awaiting Consents
- Exeter (Tertiary)England and Wales, Storage with solar or windStage 2: Capacity changed from 57 MW to 7.1 MW
- Exeter (Tertiary)England and Wales, Storage with solar or windStage removed (49.9 MW from 1 Nov 2025)
- Exeter (Tertiary)England and Wales, Storage with solar or windTechnology changed from Storage to Storage, Solar
- Exeter (Tertiary)England and Wales, Storage with solar or windNew stage added (49.9 MW from 6 Dec 2036)
- Exeter (Tertiary)England and Wales, Storage with solar or windNew stage added (57 MW from 6 Dec 2036)
- ManningtonEngland and Wales, Storage with solar or windCapacity changed from 49.9 MW to 47.5 MW
- Kirkby (Tertiary)England and Wales, Storage with solar or windConnection date moved from 31 Oct 2025 to 30 Aug 2027 (+22 months)+22 mo
- CarringtonEngland and Wales, StorageTechnology changed from Storage, Solar to Storage
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?