PIVOTED POWER LLP

Customer named in the TEC register

27projects in the register
1.2 GWstill to connect
0 MWof that with Gate 2 offers
307 MWconnected now

Projects

ProjectConnection siteTechnologyQueued MWConnection dateGateStatus
Seabank (Tertiary)SEABANK 400/33kV SUBSTATIONStorage49.91 Nov 2023 Past dateGate 1Awaiting consent
Indian QueensIndian Queens 400kV SubstationStorage47.530 Jul 2024 Past dateNot statedConsented
BraintreeBraintree 400kV SubstationStorage with solar or wind5730 Oct 2024 Past dateNot statedAwaiting consent
ManningtonMannington 400kV SubstationStorage with solar or wind47.530 Nov 2025 Past dateNot statedConsented
NorwichNorwich Main 400kV SubstationStorage with solar or wind5718 Dec 2025 Past dateNot statedConsented
LandulphLandulph 400kV SubstationStorage with solar or wind5718 May 2026 Past dateNot statedConsented
WillingtonWillington East 400kV SubstationStorage5730 Jun 2026 Past dateGate 1Scoping
Oldbury (Tertiary)Oldbury 275kV SubstationStorage5730 Jun 2027Gate 1Awaiting consent
Kirkby (Tertiary)Kirkby 275/33kV SubstationStorage with solar or wind5730 Aug 2027Gate 1Scoping
AxminsterAxminster 400kV SubstationStorage49.931 Oct 2027Gate 1Scoping
WhitsonWhitson 275kV SubstationStorage49.931 Oct 2027Gate 1Scoping
Exeter (Tertiary)Exeter 400kV SubstationStorage with solar or wind5716 Jun 2028Not statedAwaiting consent
CarringtonCarrington 275kV SubstationStorage5731 Oct 2028Gate 1Awaiting consent
KearsleyKearsley 275kV SubstationStorage49.931 Oct 2028Not statedAwaiting consent
Sellindge (Tertiary)Sellindge 400kV SubstationStorage7631 Oct 2028Not statedAwaiting consent
SpennymoorSpennymoor 400kV SubstationStorage49.931 Oct 2028Gate 1Awaiting consent
Burwell (Tertiary)Burwell Main 400kV SubstationStorage5730 Jun 2029Not statedAwaiting consent
AlverdiscottAlverdiscott 400kV SubstationStorage10031 Oct 2029Gate 1Scoping
Pivot Power Harker HybridHarker 400/132KV SubstationStorage with solar or wind5731 Oct 2029Gate 1Consented
BolneyBolney 400kV SubstationStorage with solar or wind47.531 Jan 2031Not statedScoping
TauntonTaunton 400kV SubstationStorage10031 Oct 2031Gate 1Awaiting consent
BredburyBredbury 275kV SubstationStorage0ConnectedNot statedBuilt
BustleholmeBustleholm GSPStorage0ConnectedNot statedBuilt
CoventryCoventry 275kV SubstationStorage with solar or wind0ConnectedNot statedBuilt
CowleyCowley 400kV SubstationStorage0ConnectedNot statedBuilt
KemsleyKemsley 400kV SubstationStorage0ConnectedNot statedBuilt
Sundon Pivoted PowerSundon 400kV SubstationSolar0ConnectedNot statedBuilt

Recent changes

No changes here since 14 Aug 2026.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose